Construction Progress of the New Wastewater Treatment Project at Pucheng Clean Energy Chemical Co., Ltd.
Release time:
2018-05-21
Source:
Project Name:Pucheng Clean Energy Chemical Co., Ltd. New Wastewater Treatment Project
Project Location:Southern part of Weibe Coal Chemical Industrial Park, Pucheng County, Shaanxi Province
Contract Content:Equipment installation, non-standard equipment manufacturing and installation, steel structure manufacturing and installation, process piping installation, electrical installation, and instrumentation installation.
Construction Unit:Pucheng Clean Energy Chemical Co., Ltd.
Supervision Unit:Shengli Oilfield Xinxing Engineering Supervision and Consulting Co., Ltd.
Design Unit:Hualu Engineering Technology Co., Ltd.
General Contractor/Construction Unit:Shaanxi Construction and Installation Group Co., Ltd. Third Engineering Company
Contract Amount:7,760,519.35 Yuan
Start and Completion Time:Start TimeNovember 16, 2016 Completion Time May 30, 2017
Creation Goal:All engineering quality is qualified, creating a provincial-level safe and civilized construction site
Current Project Progress:Wastewater treatment device (472) Anaerobic reactor construction completed; pipeline materials arrived, construction started; equipment drawings not yet issued; electrical drawings issued on February 11, 2017, in the material preparation stage; instrument drawings not yet issued.