Construction dynamics of new sewage treatment project of Pucheng clean energy Chemical Co., Ltd

Construction dynamics of new sewage treatment project of Pucheng clean energy Chemical Co., Ltd

(Summary description)the main body of anaerobic reactor of sewage treatment unit(472)has been completed;Pipeline materials arrive at the site and construction has started;Equipment drawings are not issued;The electrical drawings were issued on February 11,2017 and are in the material preparation stage;Instrument drawings have not been issued.

Construction dynamics of new sewage treatment project of Pucheng clean energy Chemical Co., Ltd

(Summary description)the main body of anaerobic reactor of sewage treatment unit(472)has been completed;Pipeline materials arrive at the site and construction has started;Equipment drawings are not issued;The electrical drawings were issued on February 11,2017 and are in the material preparation stage;Instrument drawings have not been issued.

Information

Project Name:new sewage treatment project of Pucheng clean energy Chemical Co.,Ltd
Project location:South of Weibei Coal Chemical Industrial Park,Pucheng County,Shaanxi Province
Contracting contents:equipment installation works,non-standard equipment production and installation works,steel structure production and installation works,process pipeline installation works,electrical installation works and instrument installation works.
Employer:Pucheng clean energy Chemical Co.,Ltd
Supervision unit:Shengli Oilfield Xinxing Engineering Supervision Consulting Co.,Ltd
Designer:Hualu Engineering Technology Co.,Ltd
General contractor/construction unit:the third engineering company of Shaanxi Construction Engineering Installation Group Co.,Ltd
Contract amount:7760519.35 yuan
Commencement and completion time:November 16,2016 and May 30,2017
Creation goal:the project quality is all qualified and a provincial safe and civilized construction site is created
Current project progress:the main body of anaerobic reactor of sewage treatment unit(472)has been completed;Pipeline materials arrive at the site and construction has started;Equipment drawings are not issued;The electrical drawings were issued on February 11,2017 and are in the material preparation stage;Instrument drawings have not been issued.

Scan the QR code to read on your phone

The group adheres to the corporate philosophy of "building for the good", adheres to the core values of "people-oriented innovation, responsibility, cooperation and win-win", implements the development strategy of "investment, construction ...

黔东南演艺集团

WeChat

Copyright © 2022 Shaanxi Construction Engineering Installation Group Co., Ltd.   陕ICP备14012471号  Powered by www.300.cn  seo