Construction progress of the Huawei terminal project in Songshan Lake
Release time:
2018-04-11
Source:
Construction Progress of Huawei Terminal Project in Songshan Lake
Project Overview:The Huawei Terminal Project in Songshan Lake is located in the Songshan Lake Scenic Area, Songshan Lake Management Committee, Dongguan City. It is Huawei's largest comprehensive office complex project in China. Covering 1900 mu (approximately 126.7 hectares) with a construction area of approximately 1.5 million square meters, it is Huawei's largest ongoing construction project.
Project Name:Phase I Integrated Electromechanical Package Project of Huawei Songshan Lake Terminal
Project Location:South side of Songshan Lake Ring Road, Songshan Lake Management Committee, Dongguan City
Contract Content: HVAC, water supply and drainage, and electrical engineering for Group 4-1 and Group 4-6.
Construction Unit:Huawei Investment Co., Ltd.
Supervision Unit: China Oceanwide Supervision Co., Ltd.
Design Unit: Nikken Sekkei/Shenzhen Huayang International Engineering Design Co., Ltd.
General Contractor:China Construction Third Engineering Bureau
Construction Unit:Undertaken by the Group's Second Engineering Company
Project Management Team:Project Manager (Liu Le), with 2 production managers, 1 technical director, 1 business manager, 8 professional foremen, 2 safety officers, 1 quality inspector, 1 materials manager, 1 materials clerk, 1 warehouse manager, 1 document/labor and wages clerk, and 3 interns, totaling 22 management personnel.
Contract Amount:142 million yuan
Start and Completion Time:2015.7.15—2017.5.30
Creation Goals:
1. Contract Fulfillment Goal:Complete project handover to the owner by May 30, 2017.
2. Owner Evaluation Goal: Achieve Huawei's A-level evaluation in 2016, strive for the title of Huawei's excellent project team, and contribute to the strategic cooperation between the group company and Huawei.
Project Progress:
Due to design adjustments, the project delivery date has been adjusted from the original contract date ofMay 30, 2017, to May 30, 2018. Currently, our companyhas completed the electromechanical engineering construction tasks for the two groups we undertook and is currently undergoing joint commissioning. The plan is tocomplete the electromechanical commissioning of Group 1 by April 30, 2018, and Group 6 by May 15, 2018, with the overall handover to the owner scheduled for May 30, 2018.The following is an aerial view of the completed project.
The following is an aerial view of the completed project