Xi'an Liangjiatan International School Project Construction Engineering
Release time:
2018-05-21
Source:
The Xi'an Liangjiatan International School project's construction and installation engineering is a self-operated project of the Group's Fifth Engineering Companyprojectand is also a key project this yearThe contract amount is approximately100 million yuan。
Project Overview
(1)Project Name: Xi'an Liangjiatan International School Comprehensive Building Electromechanical Installation General Contracting Project
(2)Project Location: Lingfeng East Road, Xi'an International CommunityEast side
(3)Main Construction Scope:
Recycled water and rainwater treatment;Roof steel structure, light steel canopy project;Air conditioning project;Weak current project;Outdoor project;Deep geothermal dry hot rock project;High-end decoration electrical, sanitary ware project;High-end decoration pipeline project.
Construction Unit: Xi'an Gaoko International Community Construction and Development Co., Ltd.
Supervisory Unit: Xi'an High-tech Construction Supervision Co., Ltd.
Design Unit: China Construction Northwest Design and Research Institute
General Contractor:China Railway Twelfth Bureau Group Co., Ltd.
Project Management Team:Project Manager: Yun Xiaoming, Deputy Project Manager: Wang Wenping, Safety Officer: Wei Jie, Technician: Li Weipeng, Documentarian: Wang Xin, Quality Inspector: Yun Deng.
Start and Completion Time:2017.04.01—2017.09.30,Total Construction Period183 calendar days.
Quality Goal:Achieve qualifiedstandard。
CurrentProject Progress Status:
Ventilation Project: School Comprehensive Building98% of the air duct installation in Area A of the school comprehensive building is completed. 30% of the air ducts in Area B are completed. 95% of the air duct insulation in the comprehensive building is completed. The overall air conditioning system has completed 80% of the total project volume.
Outdoor Project: CompletedW24_7-W24-9, Y1-Y3; Y41_5-Y41_7_3; Y10--Y12 excavation, pipe laying, well construction, backfilling. W5-W6, Y20_5-Y20_9; Y25-Y30W12_1-W12_3 excavation, pipe laying, well construction. Y31_Y34 excavation. One oil storage pool, one sand settling tank, and two flushing wells are reinforced. 40.3% of the total project volume has been completed.
High-end Decoration Electrical Part: CompletedKO+640—KO+940 section street lighting power pipe laying, 59.3% of the total project volume has been completed.
High-end Decoration Pipeline: School Comprehensive BuildingInstallation of refrigerant pipes in Area A is completed; branch pipes on floors 1, 2, and 3 of Area B of the air conditioning water system in Section B are completed; air conditioning water on the first floor of Section C is completed; multi-unit air conditioners are installed in the comprehensive building.
Steel structure project has been completed.
The dry heat source project has successfully assembled the wellhead and started drilling the first well, which has now been drilled2100 meters.