Construction progress of the Puyang County urban heating project
Release time:
2018-05-21
Source:
Construction Progress of Puyang County Urban Heating Project
The Puyang County Urban Heating Project is located in Puyang County, Henan Province, with a signed contract price of approximately500 million RMB. The contract duration is 450 days, with a planned start date of July 1, 2017, and a planned completion date of September 30, 2018. The engineering quality standard is qualified. This project is undertaken by the Group's Henan Engineering Company, with project manager Lan Wenxiong; projectThe construction unit is Puyang Yukai Baicheng Construction Co., Ltd., and the design unit is China Municipal Engineering North China Design and Research General Institute Co., Ltd.,The supervision unit is Henan Xinhengfeng Engineering Consulting Co., Ltd.
The Puyang County Urban Heating Project is a key project invested by the Puyang County government and a public welfare project providing centralized heating for businesses within the urban heating area. The heat source is the Puyang Longfeng Thermal Power Plant (2×600MW) heating units. The planned pipeline length is approximately70Km,pipe diameterDN800/600/500, supply and return water double-pipe laying, design pressure 1.6MPa, heating medium is 130/70℃ hot water. This project mainly adopts uncompensated cold installation, with local compensation devices installed in the pipeline, and prefabricated insulated pipes are buried directly.
Pipe material isQ235-B, insulation material is polyurethane rigid foam plastic, outer protective pipe material of insulated pipe is high-density polyethylene, compensator adopts direct-buried bidirectional flow external anti-corrosion unfixed support unidirectional sleeve compensator, pipeline welding adopts argon arc welding or downward welding, and all welds are 100% radiographic tested.
Current construction progress: The project construction content includes the laying of heating pipelines and the construction of supporting facilities, and it is a design-as-you-go project. The project department
entered the site on June 1, 2017, and has completed the design drawings for four streets. 48 million yuan worth of pipe materials and accessories have been ordered, and some pipe materials have been entering the site successively, and the work surface is gradually expanding. A total of approximately 8Km of construction enclosures have been completed, 2270m of trenches have been excavated, 1080m of pipelines have been welded, and 330m of pipe jacking has been completed. 870m of concrete pavement demolition and garbage removal has been completed.