Samsung (China) Semiconductor Co., Ltd. 12-inch flash memory chip Phase II project - wastewater reuse building project --- electrical engineering PKG1 construction dynamic
Release time:
2019-03-28
Source:
Samsung (China) Semiconductor Co., Ltd.in the Phase 2 project of 12-inch flash memory chips
Wastewater Reuse Building Project---Electrical EngineeringPKG1 Construction Progress
1Project Name: Samsung (China) Semiconductor Co., Ltd.12inch flash memory chip Phase 2 project
Wastewater Reuse Building Project——Electrical EngineeringPKG1
2Project Location: Xiaohe North Road, Xi'an High-tech Zone1999No.
3Contract Content: Lighting equipment engineering, electric heating equipment engineering, grounding/Lightning protection equipment engineering, Tel,LANEquipment engineering, broadcasting equipment engineering,CCTVEquipment engineering,TRSEquipment and other projects.
4Contract Amount:48410437.00Yuan
5Project Start and Completion Dates:2018Year5Month28Day——2019Year8Month31Day
6Project Quality: Give priority to meeting the quality standards stipulated in the contract of the client, construction unit and project management execution unit, and meet the qualified standards of the current national construction and acceptance specifications.
6Construction Unit: Samsung (China) Semiconductor Co., Ltd.
7General Contractor: China Construction Fifth Engineering Bureau Third Construction Co., Ltd.
8Construction Company: Shaanxi Construction and Installation Group Co., Ltd.
9Survey Unit: Machinery Industry Survey and Design Research Institute Co., Ltd.
10Design Unit: Shiyuan Technology Engineering Co., Ltd.
11Supervision Unit: Shaanxi Chengxin Supervision Co., Ltd.
12Project Management Team: Project Manager: Liu Zhen Production Manager: Long Yan Project Department includes
Construction Management:2 people, Quality Management:1people Data Management:1people
Material Management:1 person Safety Management:3people Korean construction management personnel:5people
General Affairs Group:2 people Design Group:2people Quality Group:2people Translation:4people Warehouse Keeper:3 people
13Project Progress:2018Year5Month~6Month Completion of Hotline Equipment Engineering,2018Year6Month~8Month Completion of Broadcasting Equipment Communication Engineering,2018Year7Month~8Month Completion of Lighting and Electric Heating Equipment Engineering,2018Year8Month~9Month Completion of Grounding/Lightning Protection Equipment Engineering,2018Year10Month~2018Year12Month Lighting Equipment Engineering Construction Started,2019January~2019Year5Month began to gradually complete other sub-projects.2019Year6Month~2019Year7Month Cooperate with the client for system commissioning.2019YearAugust Completion of Completion Acceptance.