Construction progress of the intelligent installation project of the three halls in Tongchuan
Release time:
2019-06-25
Source:
Intelligent System of Tongchuan Three HallsInstallation Project Construction Progress
1、Project Name:Intelligent System Project and Outdoor Flood Lighting Project of Tongchuan Three Halls
2、Project Location: Shaanxi ProvinceTongchuan City, TongchuanNew District
3、Contract Price:To be determined3000Ten thousand yuan
4、Construction Start and Completion Time:900 calendar days
5、Construction Unit:Tongchuan Chuangyue Construction Project Management Co., Ltd.
6、Design Unit:China Construction Northwest Architectural Design & Research Institute, Shaanxi Construction and Installation Group Co., Ltd.
7、Supervision Unit: /
8、Project Quality Goal:Chang'an Cup, National Excellent Engineering Award
9、Safety and Civilized Construction Goal: Provincial Civilized Construction Site, Green Demonstration Project
10、Construction Content:Intelligent system project and outdoor flood lighting project of Tongchuan Three Halls, involving pipes, wires, cable trays, cabinets and boxes, and the installation and commissioning of all system equipment.
11、Project Management System: Project Manager:Han Chao
Technical Leader:Yong Anji,Foreman: Zhang Zhao,Safety Officer:Yang Wei,Quality Inspector:Hu Xiao,Materials Officer:Ma Chenyang
12、Current Construction Progress:
(1)Tongchuan Museum
Main body pre-embedding,Secondary pipingConstruction completed.
(2)Tongchuan Workers' Palace
Secondary piping, cable tray installation, cable laying completed100%; 30% of intelligent equipment installation completed.
(3)Tongchuan Grand Theatre
Drawing clarification, piping completed20%.