Malaysia Integrated Phosphochemical EPC Project Phase 1 Project Dynamic
Release time:
2019-05-31
Source:
1. Project Name: Integrated Phosphate Chemical Plant, MalaysiaEPCProject1Project Phase
2. Project Location: Samalaju Industrial Park, Bintulu, Sarawak, Malaysia
3. Contract Price:8000Million USD (equivalent to5.28Hundred Million RMB)
4. Construction Period:2018Year9Month1Day to2020Year11Month30Day
5. Client:Malaysian Phosphate Additives (Sarawak) Sdn. Bhd.
6. Design Institute: SINOPEC Nanjing Engineering Company
7. Supervisor:/
8. Project Quality Goal: Meet Malaysian local standards
9. Safety and Civilized Construction Goal: Meet Malaysian local standards
10. Construction Content: Annual output of4.8thousand tons of yellow phosphorus unit, annual output of7.5thousand tons of thermal phosphoric acid unit, annual output of6thousand tons of food-grade phosphoric acid unit and supporting public works design, procurement and construction work.
11. Project Management System:
Project Manager: Hu Chunlin
Deputy Project Manager: Huang Zhu
Procurement Manager: Bai Shengli
Design Manager: Zhang Weitao
Quality Manager and Procurement Technical Officer: Zhang Liguo
Design Coordination: Guo Huichuang, Wang Chenguang
Technical Consultant: Du Jianxue
Safety Officer: Wang Xiaojun,Hon Siaw Choi (Malaysian),Asri(Malaysian)
Construction and Quality Inspectors: Feng Weibao, Zhao Dahai, Cao Yukun, Zhu Zhiping, Duan Songchao, Wei Xingzhou,
He Jinbiao, Su Hao, Fang Haowen
Materialists: Tian Wushe, Guo Tan
Project Finance and Labor Relations: Ren Xiangbin, Lei Mengchao
Planning, Control and Business Management: Yan Yutong, Liu Xiaohan, Peng Shuo
English Translator: Lou Lingwen
Visa Management: Liu Zhao
Administration and Logistics: Yu Hua
12. Current Progress:
(1) Design Work: Process design, equipment selection and layout are completed, and general and construction drawings are completed.85%。
(2) Procurement Work: Orders for process equipment are all completed, and all have started factory manufacturing. The yellow phosphorus electric furnace equipment has been delivered;
Steel structure orders are completed80%, and factory manufacturing has begun. The phosphate rock warehouse truss structure has been shipped;
Process pipelines and materials are undergoing Bidding;
Electrical equipment and materials are undergoing Bidding;
(3) Construction Work: The main civil structure of the yellow phosphorus main plant and the yellow phosphorus unit control room is completed;
The civil foundation construction of the food-grade phosphoric acid plant and the mixing station is completed;
Mud phosphorus treatment section, cooling circulating water station, yellow phosphorus storage tank, thermal phosphoric acid storage tank foundation completed;
Phosphate plant area substation civil foundation construction in progress;
Installation of yellow phosphorus electric furnace equipment is in progress;
13. Technical Highlights:
Use industrialBIM technology to model the entire plant's building structure, equipment, and pipelines, and dynamically manage them during equipment procurement and construction.