Shenmu City Urban District Central Heating Project Construction Progress
Release time:
2019-09-28
Source:
1. Project Name: Shenmu City District Central Heating Project
2. Project Overview: The Shenmu City District Central Heating Project is a major construction project in Shenmu City in 2018, with a total investment of approximately5.26hundreds of millions of yuan. The investment in the heating installation project is approximately380 million yuan. This project includes the construction of a new primary hot water pipe network41kilometers (DN200~DN1400), and a new intelligent heat dispatch center (including pressure regulating stations)1sets. The maximum heating radius of the primary heating main network is26.6 kilometers.
3. Construction Progress: The DN1400 primary heating pipe network has been fully completed; the full-line pipe pressure test and flushing work has been completed. The pressure regulating station installation project has been completed 100%. The first phase of the heating pipe network has been completed on schedule, and is currently undergoing cold-state commissioning. This project is proceeding on schedule for centralized heating.
4. After the completion of the Shenmu City Central Heating Improvement Project, Shenmu City will achieve full coverage of centralized heating from the thermal power plant, with 100% ultra-clean emission of heat sources, full-process intelligent monitoring of the heat network, 100% automated control (unmanned) of regional heat stations, and 100% use of new energy-efficient and pollution-free materials and equipment in newly built heating facilities. Shenmu City will become a key demonstration area in northern China's centralized heating cities with first-class quality, equipment, technology, and management.
Previous Page
Related News
2023-10-27