Construction progress of the N1 section of the Yunen Guofang Hotel building installation project
Release time:
2019-10-22
Source:
1. Project Name: Yulin Energy Construction Guofang Hotel Building Installation Project N1 Section
2. Project Location: Binhe New Area, Shenmu City, Yulin City
3. Contract Price: Provisionally 48.51 million yuan
4. Construction Duration: 300 calendar days
5. Construction Unit: Yang Huopan Coal Mine, Yulin City
6. Supervision Unit: China Coal Shaanxi Zhong'an Project Management Co., Ltd.
7. Construction Content: Air conditioning and ventilation engineering, water supply and drainage engineering, high and low voltage power engineering, reclaimed water treatment system engineering, swimming pool water treatment engineering, bath water treatment engineering, laundry room system engineering, gas boiler system procurement and installation engineering, and wall renovation engineering.
8. Project Management System: Project Manager: Zhu Jiangtao
Technical Director: Gu Jia, Foremen: Han Yong, Wang Junfeng, Li Xiaonan, Yang Ben, Safety Officer: Chen Liang, Materials Officer: Wu Yang, Warehouse Manager: Chen Bin, Interns: Lü Wei, Jia Wangduo
12. Current Construction Progress:
(1)Main Building 7-23 Floors
Ventilation pipes, air conditioning water pipes, water supply and drainage pipes, and electrical cable trays are 90% complete.%,Cables are being laid, and equipment is awaiting installation.;
(2)Main Building 1-6 Floors
Ventilation pipes, air conditioning water pipes, water supply and drainage pipes, and electrical cable trays are 90% complete.%,Cables are being laid, and equipment is awaiting installation.;
(3)Annex Building 1-6 Floors
Ventilation pipes, air conditioning water pipes, water supply and drainage pipes, and electrical cable trays are 50% complete.%,Water supply and drainage are under construction, cables are awaiting laying, and equipment is awaiting installation.;
(4)Basement
Ventilation pipes, air conditioning water pipes, water supply and drainage pipes, and electrical cable trays are 70% complete.%,Water supply and drainage are under construction, cables are being laid, and equipment is awaiting installation.