Construction progress of the Kechuang Wisdom Park (Phase I) EPC general contracting project
Release time:
2020-01-13
Source:
Construction Progress of the Kechuang Wisdom Park (Phase I) EPC General Contracting Project
1, Project Overview
The Kechuang Wisdom Park (Phase I) project is a key livelihood project in Xixian New District. This project is divided into A andBtwo plots of land, with a total land area of5.3square meters and a total construction area of4square meters. Among them,Building No. 1(3floors),Building No. 2(3floors),Building No. 3(3floors),Building No. 4(3floors),Building No. 5(2floors),Building No. 6(2floors) are research and development workshops7800square meters,Building No. 7(basement1floor, above ground3floors) The basement floor is a high and low voltage distribution room, living and fire water pump room,Building No. 8(2floors) is a supporting facility building with a construction area of3700square meters, parking spaces for448vehicles, and non-motorized vehicle spaces for840vehicles.
The Kechuang Wisdom Park (Phase I) project scope of work includes: main construction of eight buildings and internal supporting electromechanical installation; public area decoration; external curtain wall installation; overall outdoor roads, landscaping, floodlights, underground sewage, rainwater, outdoor fire hydrant pipes, outdoor sprinkler pipes, outdoor water supply pipes and cable laying.
Construction Unit: Xi'an Silk Road Innovation Development Co., Ltd.
Design Unit: Shaanxi Tongji Civil Engineering and Architectural Design Co., Ltd.
Supervision Unit: Xi'an Sifang Construction Supervision Co., Ltd.
Construction Unit: Shaanxi Construction Engineering Installation Group Co., Ltd.
2, Project Management System
Project Manager: Li Bingshu
Executive Manager: Fan Wenjin
Technical Manager: Su Peilong
Production Manager: Zhao Jiale
Safety Manager: Ma Hongchao
Business Manager: Li Jialiang
Professional Foremen: Sha Shengbing, He Zhen, Miao Haipeng, Chen Geng, Zhang Wei; Safety Officers: Fang Xiaoyu, Gao Pan; Materialists: Li Chao, Ding Xiaohong; Equipment Personnel: Lv Hongwei; Quality Inspectors: Cai Shinong; Documentarians: Liu Ruiling
3, Current Construction Progress
The main structures of Buildings 1-8 have been completed.100%;
Buildings 1-6,Building No. 8External curtain wall construction completed100%,Building No. 7External curtain wall construction completed90%;
Buildings 1-6,Building No. 8Building fire water system completed100%,Building No. 7Building fire water system completed90%;
Electrical piping and trunking completed for Buildings 1-8100%;
Outdoor parking spaces completed 95%, landscaping completed95%,Outdoor comprehensive pipelines completed95%.