Unchanged goals, undiminished tasks, and unwavering assessment—the Group Company is fully launching a wave of resuming work and production
Release time:
2020-03-10
Source:
To recover the losses caused by the epidemic, the GroupFollowing the leadership team meeting on March 6th, which emphasized the importance of not relaxing efforts in epidemic prevention and accelerating production to sound the charge for the resumption of work and production, the company once again actively responded to and implemented the call issued by Shaanxi Construction Group on March 7th, which stated that the goals remain unchanged, the tasks remain the same, and the assessments remain strict, to ensure the dual victory of epidemic prevention and control and achieving the annual goals and tasks, and issued the strongest call for resuming work and production.
Currently, more than 100 projects under construction by the Group have resumed work and production, with1600 people returning to their posts.
Shengan Plaza Project:More than 500workers are working together
In themorningatMunicipal
Construction Company's Shengan Plaza project, workers are setting up formwork, tying steel bars, pouring concrete, laying partition walls, installing pipes, and laying cable trays, actively and orderly carrying out various tasks in a busy atmosphere.Since
resuming work on February 25th, the Shengan Plaza project department of the Municipal Construction Company, while implementing various epidemic prevention measures, strengthened organizational management, scheduled construction plans in reverse order, clarified nodal objectives, and implemented personnel and materials and other production factors, upholding a spirit of hard work to ensure strong progress.On March 5th, within just a few days, the project department hadmore than 300workers entering the site for work,10On MarchMore than 500the number even reached
providing manpower support for achieving the target of opening in November.The project department, foreseeing potential issues, had stockpiled
more than 200 cubic meters of bricks, more than 100 tons of steel bars, and more than 50 tons of mortar before the new year, enough to meet the project's needs for two months. The sufficient materials made the resumption of work and production seem unhurried.Currentlythe project'smain structure has been completed, the office,C garage construction has reached the -1 floor, the office A secondary structure has reached the 11th floor, the office B secondary structure has reached the 11th floor, and the office C secondary structure has been completedOfficeC exterior wall insulation has been completed
and all work is progressing smoothly.
Pingliang Natural Gas Project: Technological Breakthrough Recognized
Recently, the Pingliang natural gas project of the Twelfth Company achieved a breakthrough in the key technology of Jianhe directional drilling crossing. Pingliang TV reported on the project's epidemic prevention and control and resumption of work and production, and the project department also received high praise from the local government and the construction unit.Horizontal directional drilling technology can be called
“three high technologies”, namely high technology, high efficiency, and high risk. The Jianhe directional drilling crossing is the key and difficult point of the entire project, and it directly restricts the overall progress of the entire project. The construction site has complex and diverse terrain and harsh traffic conditions, requiring the widening and repair of the access road for the drilling rig. The directional drilling crosses the ditch bottom in a V-shape from the northern bank to the southern bank, with a total crossing length of approximately 1800 meters and a vertical drop of approximately 169 meters, with a design coefficient of 0.5.
For this difficult project, the project department developed a special construction plan, pooled ideas to supplement the plan, and organized technical, quality, and safety professionals to review and revise it. The project strictly controlled the construction process and checked the construction quality at every level, ultimately successfully overcoming this rare technical difficulty in the construction technology of the Northwest region, strictly ensuring the project schedule, and ensuring that the construction was completed once and with high quality.
Yulin Chemical Ethylene Glycol Project: Reclaiming Lost TimeAt 8 p.m. on February 27tha work meeting organized by the owner just ended.The projectmanager, Li Shoushan, pushed open the door of the meeting room. The still biting cold wind outside made him shiver, but that was nothing compared to the contents of the meeting that weighed on his chest—the owner had advanced the original completion acceptance deadline of the end of April to the end of March.The project schedule, already tight due to the epidemic,,became even more tense.This is a scene that took place at the Yulin Chemical Ethylene Glycol project of the Third Company.。
“The battle is far from over, and the war drums are beating again.”The project departmentscheduled the work backward, readjusting the construction plan. The construction site was brightly lit at night, with the roar of engines. Construction workers performed their duties, working hard, working overtime, and operating at high speedBy now24 management personnel, 160 front-line construction personnel, and 25 various types of machinery have been put into production.One morning,Li Shoushan, having just finished breakfast and rushed to the construction site, suddenly found that the hundreds of meters of trenches excavated overnight had been refilled by the wind and sand, causing the trench depth to not meet the requirements for pipe laying. The low temperature at night had also turned the sand into a thick layer of frozen soil, further increasing the difficulty of re-excavating the trenches. Time was of the essence. Faced with this situation, Li Shoushan quickly dispatched teams, with jackhammers working on the frozen soil layer in front, and construction workers using shovels to remove the loosened soil layer from the trench. At the same time, he arranged for the crane to lay pipes and organized welders to conduct pipe joint welding. It was under this strong cooperation and high-intensity and high-efficiency construction pace that the project department successfully completed the trench repair and pipe installation work, laying a solid foundation for the smooth progress of the next day's work.
“,刚吃完早饭赶赴施工现场的李寿珊突然发现,前一晚加班加点挖掘的百余米长的管沟被漫天的风沙回填了许多,导致管沟深度达不到布管要求,且夜间的低温将原本的沙土变为一层厚厚的冻土,更是增加了重新开挖管沟的难度。时不我待,面对这种情况,李寿珊急调班组,前面电镐对冻土层作业,后面施工人员用铁锨将松动的土层扔出管沟,同时安排吊车布管并组织焊工进行管道对口焊接工作。正是在这种通力合作,高强度、高效率的施工节奏下,项目部圆满完成了管沟补救和管道安装工作,为第二天施工任务的顺利进行打下了坚实的基础。
“To prepare for war and strive for rapid progress,Tomake up for lost timeLi Shoushan said so.
Ankang Airport Fuel Supply Project: Commendation for Promoting Resumption of Work
Recently, the Second CompanyAnkang Relocation Airport Fuel Supply ProjectWhile fully focusing on epidemic prevention and control, actively organized various professional construction personnel to resume work and production, becoming the first project among the 49 projects under construction of China Aviation Oil Northwest Company to resume work, setting an example for other projects and receiving affirmation and praise from the construction unit.It became a model for other projects and received affirmation and praise from the construction unit.
The project resumed work on February 17, and on February 228management personnel were in place,42 technical workers entered the site, and on February 23, the project department fully resumed production. Because the project department planned to resume work on the sixth day of the first month before the year, the construction materials on site were well prepared. May is the rainy season in Ankang. In order to complete the outdoor pipe network and tank foundation construction before the rainy season, the project department sorted the construction sequence of cross-operations and made a reverse schedule for the remaining engineering items. On February 25, the number of construction personnel in the project department reached 65, fully meeting the current labor requirements.
Currently, the project department's perimeter wall construction is completed50%, and the tank foundation, fire break foundation, and accident water pool foundation have completed steel bar binding, formwork erection, and concrete pouring. In order to more effectively promote the construction progress, the project department has arranged night shift work and formulated safety measures for night shift work.
Luzhou Liquor Industry Park Project: Government Recognition for Epidemic Prevention and Control
On March 1, Liu Qiang, Secretary of the CPC Luzhou Municipal Committee, and Yang Linxing, Deputy Secretary of the CPC Municipal Committee and Mayor, visited the wastewater treatment plant expansion project of the Luzhou Liquor Industry Park of Chongqing Company to inspect and guide the epidemic prevention and control and resumption of work and production. They fully affirmed the implementation of epidemic prevention and control measures on site.
Since the outbreak of the epidemic, the project department, firstly, strictly followed the arrangements and deployments of the group company on epidemic prevention work, and combined with the actual situation in Luzhou to establish a prevention and control management system, formulate practical prevention and control plans and emergency plans, and implement prevention and control responsibilities at all levels; secondly, carry out publicity and education on epidemic prevention and control among employees, implement separate meals, conduct body temperature checks twice a day before and after work,draw maps of employees' outdoor activities, and conduct nucleic acid tests for personnel returning from other provinces; thirdly, set up an independent isolation and observation room, with one person per dormitory room, and disinfect areas where personnel gather, such as workplaces, twice a day.
Sixth Company: Secondary Business Boosts Morale
Recently, the Sixth Companysuccessfully bid for"Shangqiu City's Third Wastewater Treatment Plant Phase II Equipment Procurement and Installation and Debugging, General Plan Pipeline Project" with 82.99 million yuan. This project mainly includes the procurement and installation of equipment for the entire plant, the general plan outdoor pipeline network, equipment and water quality debugging, training and technical services. This project is the second business successfully achieved by the Sixth Company with the owner after the successful completion of Shangqiu's Second Sewage Treatment Plant.
With the strong support of the Group's leadership and sister units such as the Fourth Company, the Sixth Company has always adhered tothe core values of "customer and project-centric", organized scientifically, carried out meticulous construction, and worked with the spirit of craftsmanship on every detail, ensuring that the quality, progress, and safety of the project were always in a leading position, winning high praise from the owner, and enabling successful bidding. This successful bid has injected strong momentum into the Sixth Company's 2020 market development work and created a good start for completing the tasks for the whole year.