Construction progress of Cangzhou Zhongliang Guancanghai general contracting project
Release time:
2020-02-28
Source:
Cangzhou Zhongliang Guancanghai ConstructionGeneral ContractingProject
Construction Progress
1、Project Overview
ThisProjectis a high-rise residential complex and supporting buildings, locatedeast of Guizhou Avenue and north of Xi'an Road, Cangzhou High-tech Zone;Land area69927.8㎡, total construction area211098.3㎡, above-ground construction area is 154056.83㎡, underground construction area is 57041.47㎡;Including Buildings 1-19 and elderly care facilities, a total of 20 individual projects.
The underground flooris for the garage and equipment rooms, above groundResidential buildings 1-17 are 11-27 stories (except for Building 5, which is a kindergarten), with a building height of 32.9-78.8m. Building 5 (kindergarten) is three stories above ground, Buildings 18 and 19 are two-story supporting buildings, and the elderly care building is one story above ground, with a maximum building height of 12.15m. The underground garage is a frame structure with a floor height of 3.75m. The above-ground high-rise residential buildings (except for Buildings 9 and 15) are shear wall structures with a floor height of 2.9m. Building 5 (kindergarten) and Building 15 are steel structures, and Building 9 is a prefabricated shear wall structure.
ThisProject scope of contract:Foundation pit cleaning, main structure, secondary structure and rough decoration, waterproofing, electromechanical installation and other reserved and pre-embedded items, outdoor civil and installation engineering。
Construction Unit:Cangzhou Liangsheng Real Estate Development Co., Ltd.
Design Unit:Jiangsu Haosen Architectural Design Co., Ltd.
Cangzhou Architectural Design Research Institute Co., Ltd.
Supervision Unit:Hebei Xinlongji Project Management Co., Ltd.
Construction Unit: Shaanxi Construction Engineering Installation Group Co., Ltd.
2、Project Management System
Project Manager:Yao Xiangdang
Deputy Project Managers: Shen Jiebin, Wei Xianghua
Technical Head:Quan Hongsheng
Safety Manager:Liu Shangwei
Safety Officers:Ma Ziwei, Xue Nan, Shen Jieneng, Zhang Fei, Chen Jian
Business Manager: Yu Xianghua
Materials Supervisor: Chen Tao
Quality Inspectors:Cao Maolong, Shen Weiliang
Construction Workers: Fang Weiwei, Wang Fan, Huang Youshi, Huang Jin
Documentarians: Yang Lu, Han Xiaoshuang
3、Current Construction Progress
Building 1Three floorsMain body construction completed,2# BuildingSecond floor main bodyconstruction completed,3# BuildingBasement main bodyconstruction completed,
5# BuildingAllcompletedand transferred to the construction unit,6、Building 7Seven floors of main body constructioncompleted,
Building 10, three floors of main body construction completed; Building 11, basement main body construction completed;
Buildings 12 and 17, two floors of main body construction completed.