Wucangbao Joint Station Project Construction Update
Release time:
2020-03-20
Source:
Wucangbao Joint Station Project Construction Update
1. Project Overview:
Wuqi Oil Production PlantWucangbao Oilfield Ground Construction ProjectPackage 1 (within Wucangbao Joint Station)建设located in Lanshipu Village, Wucangbao Town, Wuqi County;Joint station land area53118.4m2 ;LivingAreaLand area5379.8m2 ,Building area:5428.2m2,Total requisitioned land area58498.2m2,totaling 87.75 mu;The joint station is a Class III station.。The foundation of this project adopts compacted gravel piles,Levels 1-3 adopt brick-concrete and steel structures,Wucangbao Joint Station internal engineering:Crude oil processing scale60×104t/a (Yan'an Group is 40×104t/a, Yanchang Group is 20×104t/a), wastewater treatment scale 2500m3/d (Yan'an Group is 1400 m3/d, Yanchang Group is 1100m3/d);The main contents include: Construction of a new residential area (50 people) 1 building, oil and gas gathering and transportation, wastewater treatment, water supply and drainage, fire protection, power supply and distribution, instrument automation control, thermal engineering, building and structure, HVAC system and access roads。Planned construction period18 months。
Construction unit: Wuqi Oil Production Plant
Construction contractor: Shaanxi Construction and Installation Group Co., Ltd.
Supervisory unit: Yan'an Hengruida Construction Project Consulting Co., Ltd.
Survey unit:Shaanxi Rongda Surveying and Design Co., Ltd.
Design unit: Sinopec Jiangsu Petroleum Engineering Design Co., Ltd.
2.Project Management System:
Project Manager: Lei Peng
Executive Manager: Liu Jun
Civil Engineering Manager: Zhang Zhongfeng
Specialized foremen: Zhang Zhenjun, Zong Weiwei, Li Xiaolong Materialist: Liu Jiangqi
Laboratory technician: Bi Hemen Safety officer: Dang Gangpeng, Liu Kanghui Documentalist: Zhang Li
3.Current Construction Progress:
(1)Oil and gas gathering and transportation area
Civil Engineering: Backfilling of culvert completed; Tank area leveling completed30%, drainage ditch excavation completed 20%, oil unloading pool partition wall completed, sand backfilling completed 80%, east side wastewater ditch excavation completed 60%.
Installation: Tank area and accessories installation completed, water test completed, insulation completed.
(2)Fire protection area: Wastewater ditch excavation completed.
(3)Wastewater treatment area
Civil Engineering: Steel structure and roof cladding of filter operating room completed, steel structure color steel cladding of flotation room completed, tank area piers completed, steel structure pre-embedding completed100%, firebreak completed.
Installation: Tank area and accessories installation completed, water test completed, insulation completed; Tank area pipelines completed95%, oil unloading pool pipelines completed 90%, pipeline anticorrosion and insulation completed 70%, 3 oil-gas separators, 1 gas de-oiler arrived and installation completed, valve group pipeline prefabrication and installation 30%, crude oil pump room prefabrication and installation completed 50%.
(4)Heating area
Civil Engineering:Backfilling of 3 60m³ tank foundations completed, boiler room steel structure completed, cladding completed, boiler room roof slag laying completed, parapet coping completed, indoor trenches completed, indoor equipment foundations completed, crude oil pump room main body completed 90%.
Installation: Boiler accessories installation completed, water treatment pipeline installation completed45%, process pipeline prefabrication completed 65%.
(5)Living area
Civil Engineering: Dormitory building interior plastering completed70%, roof slag laying completed, roof parapet coping completed, indoor ditches completed.
Installation: Water supply and drainage, heating pipeline fabrication completed70%, electrical and instrument, apartment building junction boxes, electrical boxes installed.
(6) Outdoor: Oil and gas gathering and transportation area firebreak coping completed 50%, access road earthwork replacement completed 60%, heating area firebreak masonry completed, east side support backfilling completed, north side pier pouring completed 80%.