Construction progress of the energy and chemical engineering building installation project at Northwest University's Chang'an Campus
Release time:
2020-04-28
Source:
1、Project Overview
The Northwest University Chang'an Campus Energy and Chemical Engineering Building project is located south of Xuefu Street, north of Fenglin North Road, within the Northwest University Chang'an Campus. It includes the energy and chemical engineering building, basement equipment rooms, and garage electromechanical installation projects. The above-ground building has fourteen floors for offices and laboratories, and the basement has one floor for a garage and equipment rooms. The building height is 63.30 meters, and the total construction area is 51903.07㎡.
The Northwest University Chang'an Campus Energy and Chemical Engineering Building project's garage and main building installation equipment includes a variety of equipment, mainly including: smoke exhaust fans, variable frequency water supply equipment, transformers, high and low voltage cabinets, and various pipes of different specifications and models.
Construction Unit: Northwest University
Design Unit: Western Construction Seismic Exploration and Design Institute
Supervision Unit: Shaanxi Provincial Engineering Supervision Co., Ltd.
Construction Unit: Shaanxi Construction and Installation Group Co., Ltd.
Project Quality Goal: Ensure "Chang'an Cup".
Safe and Civilized Construction Goal: Ensure Shaanxi Provincial Civilized Construction Site
2、Project Management System
Project Manager: Cheng Chao
Deputy Project Manager: Lei Yao
Technical Leader: Liang Feng
Electrical Foreman: Yuan Ji
Pipeline Foreman: Song Xiaoyu, Liu Chaopeng
Ventilation Foreman: Zhang Chao
Safety Officer: Chen Erfeng
Quality Inspector: Zhang Chao
Material Officer: Yue Cuilan, Xue Fuguo
2、Current Construction Progress
1) 5822 meters of cable tray installation completed 30%;
2) 2-8 floorP1086 meters of VC drainage pipe installation;
3) 2-8 floor water supplyDrainage and heating risers1241 sleeves installed;
4) 30 meters of 8-floor heating water supply and return water ring pipe installation30 meters;
5) 2-8 floor bathroom and tea room PVC pipe installation630 meters;
6) 2-14 floorPVC drainage riser installation538 meters。