Northwest University Chang'an Campus Academic Exchange Center Project Construction Update
Release time:
2020-05-11
Source:
I. Project Overview: This project is located in Northwest University's new campus in Changan District, Xi'an City, Shaanxi Province. The project name is Northwest University Changan Campus Academic Exchange Center, with one underground floor and twelve above-ground floors. The underground floor is functionally divided into partial equipment rooms, a substation, and a car park, excluding air raid shelters. The first to third floors above ground are functional spaces such as the lobby, dining area, and academic report hall. The fourth to twelfth floors above ground are a hotel. The total building area is 25098.50 ㎡, and the building height is 46.8 meters.
Scope of Work: Water supply system, drainage system, air supply and exhaust system, smoke exhaust system, power distribution system, lighting and power distribution system, building equipment intelligent control system, lightning protection and grounding protection and equipotential bonding, Tel network integrated wiring system, video surveillance system, building energy-saving control and management system, building energy consumption monitoring system, emergency lighting centralized control system.
Construction Unit: Northwest University
Design Unit: Western Architectural Seismic Exploration and Design Research Institute
Supervisory Unit: Shaanxi Provincial Engineering Supervision Co., Ltd.
Construction Unit: Shaanxi Construction Engineering Group Co., Ltd.
Shaanxi Construction Engineering Installation Group Co., Ltd.
II.Project Management System
Project Manager: Jing Zeng Project Technical Leader: Yang Xianghui Safety Officer: Yang Dongsheng, Han Zhen Quality Inspector: Yang Xiaoliang Materials Officer: Yang Xiaoliang Electrical Foreman: Cui Wei Piping Foreman: Hu Yuanyuan Ventilation Foreman: Yao Kangkai Documentarian: Liu Pengbo
III.Current Construction Progress
1. Electrical coordination work for the secondary structure of the main building's third and fourth floors is complete.
2. Electrical pre-embedding and lightning protection grounding work for the basement slab of the annex building is complete.
3. Installation of fresh air ducts in the north pipe shaft of the main building elevator has been completed up to the sixth floor.