Samsung (China) Semiconductor Co., Ltd. 12-inch flash memory chip Phase II project UT building, Green building Phase II project Green building pipeline project construction dynamic
Release time:
2020-07-09
Source:
1. Project Overview
This project is for Samsung Semiconductor Co., Ltd.12-inch flash memory chip project, located in the Xi'an Chang'an District Xitai Road Comprehensive Bonded Zone, Shaanxi Province. The project covers an area of52826m2 , the main building is a steel structure and concrete structure. The project mainly involvesthe installation of pipelines and vendor-supplied equipment in the GREEN building's basement, ground floor, and the reuse building's first and second floor wastewater treatment plant.
Project Scope:Pipelines, vendor-supplied equipment, modular installation, and ductwork for the GREEN building and the reuse building.
Construction Unit: Samsung (China) Semiconductor Co., Ltd.
Design Unit: Shiyuan Technology Engineering Co., Ltd.
Survey Unit: Machinery Industry Survey and Design Research Institute Co., Ltd.
Supervision Unit:(Stock)SanyuCMArchitectural Office(Korean side)
Shaanxi Chengxin Construction Supervision Co., Ltd.(Chinese side)
General Contractor: Shaanxi Construction Engineering Group Co., Ltd.
Specialty Subcontractor: Shaanxi Construction Engineering Installation Group Co., Ltd.
2. Management System
Project Manager: Li Qiang
Technical Leader/Business Manager: Zhu Zaiqian
Safety Officer: Liu Tao, Yuan Chuang, Zhang Yi
Construction Foreman: Liu Li, Sun Feihu, Ma Yufei, Liu Deping
Material Officer: Liang Manxia
Quality Officer: Chen Lizhi
Document Officer: Wang Cuifen
3. Current Construction Progress
GREEN Building Basement GREEN Building Ground Floor
Pipeline installation is completed80%; Pipeline installation is completed85%;
Vendor-supplied equipment installation is completed85%; Vendor-supplied equipment installation is completed30%;
Non-standard platform installation is completed25%; Non-standard platform installation is completed10%;
Deodorization ductwork installation is completed0%
Reuse Building1st Floor Modular engineering is completed55%
Pipeline installation is completed75%;
Reuse Building2nd Floor
Vendor-supplied equipment installation is completed50%; Pipeline installation is completed95%;
Non-standard platform installation is completed20%; Vendor-supplied equipment installation is completed85%;
Deodorization ductwork installation is completed0%