Construction Progress of the Electromechanical Package Project, Area A, Huawei Cloud Data Center
Release time:
2020-09-08
Source:
1. Project Overview
Project land area:71637.28㎡. Total non-data center building area:70053㎡, including: Non-data center above-ground building area:39285㎡, Non-data center underground building area:30768㎡, Total data center building area:89993㎡, including: Data center above-ground building area:70433㎡, Non-data center underground building area: 19560㎡.
The project consists of data centers and non-data centers, a total of19individual buildings, including: Data center containingA1.1/A1.2/A1.3/A2etc.5individual buildings. The main function is the data machine room. The building type is a multi-story Class C factory building, and the fire resistance grades are Class 1 above ground and Class 1 underground; Non-data centers include the basement (A4), production and delivery center(A3.1/A3.10/A3.11/A3.12/A3.13)and duty rest building(A3.2/A3.3/A3.4/A3.5/A3.6/A3.7/A3.8/A3.9/A3.14)etc.14individual buildings. The basement is mainly used as an underground parking garage; The production and delivery center is mainly used for discussion areas, discussion rooms, training rooms, coffee areas, and fitness areas; The duty rest building is mainly used for dormitories. The building type is a multi-story civil building, and the fire resistance grades are Class 1 above ground and Class 1 underground.
Construction content includes:1. HVAC: Central air conditioning system, ventilation system, and smoke exhaust system. In the system design, the principle is to meet functional needs, focusing on safety, while also considering economic rationality, energy saving, and convenient operation and management.
2. Water supply and drainage: Indoor domestic water supply system, outdoor water supply system, direct drinking water system, production water supply system, outdoor road sprinkling, green space sprinkling system, etc. Domestic sewage system, domestic wastewater system, outdoor rainwater drainage system, tea room drainage system, production drainage system, outdoor domestic sewage system, outdoor rainwater drainage system, etc.
3. Electrical:10/0.4kV power supply and distribution systememergency and backup power supply system, power distribution system, lighting system, building lightning protection, grounding system, and safety measures.
Project characteristics and difficulties: A large number of single buildings, high installation height; A large number of equipment installations, many large-scale equipment hoisting; Many types of process pipelines, complex system, including galvanized pipes, stainless steel,VAVand soft tubes; Complex electrical control system.
Construction unit: Huawei Technologies Co., Ltd.
Design unit: Guizhou Provincial Architectural Design Institute Co., Ltd.
Supervision unit: Shenzhen Zhongxing Construction Engineering Consulting Co., Ltd.
Construction unit: Shaanxi Construction Engineering Installation Group Co., Ltd.
Engineering quality target: Qualified.
2. Project Management System
Project Manager: Li Fei
Technical Leader: Zhang Dong
Construction workers: Ai Yongqi, Yun Deng, Meng Xingzhen, Liu Pengchao, Liu Zhiguo, Cao Yanping, He Yu, Xu Ke, Zhao Chongzhe
Safety officers: Cheng Wenyi, Li Junming
Quality inspectors: Hu Jianmin
Material personnel: Li Hongxin
Labor and wages personnel: Hu Wenjuan
3. Current construction progress:
HVAC, water supply and drainage, and electrical work in the A4 basement is 95% complete;
A3.2~A3.9Building HVAC, water supply and drainage, and electrical work is97% complete;
A1.1, A3.10、A3.11Building HVAC, water supply and drainage, and electrical work is75%
A3.12、A3.13、A3.14、A3.1Building HVAC, water supply and drainage, and electrical riser system construction is complete97% complete;
Equipment installation is complete606units, accounting for the total equipment amount of48%。