Construction Progress of Han River Pharmaceutical Project
Release time:
2020-10-19
Source:
Hanjiang PharmaceuticalProjectConstruction Progress
1Project Overview
This project covers a land area of 11547.21㎡ and consists of 17 individual units, including PMP workshops, API workshops, and others. It encompasses equipment, pipelines, HVAC, water supply and drainage, electrical, instrumentation, and purification engineering. MainThe main construction content includes: 7 ventilation systems, approximately 44000㎡ of ductwork; 10 process piping systems, 91000m of various pipelines; 176100 meters of cables; and installation of 3600 units of process equipment in 8 major categories.
Construction Unit: Shaanxi Hanjiang Pharmaceutical Group Co., Ltd.
Design Unit: China National Pharmaceutical Group United Engineering Co., Ltd.
Supervision Unit: China Coal Shaanxi Zhong'an Project Management Co., Ltd.
Construction Unit: Shaanxi Construction and Installation Group Co., Ltd.
Project Quality Goal: Qualified.
2Project Management System
Project Manager:Zhang Hongyun/Zhang Xiaokang
Technical Leader:Zhao Xiangyang
Construction Workers:Guo Pengfei,Su Hongchao,Han Weiru, Lu Junli, Chen Mu, Li Tianfa, Sun Maohong, Guo Jun, Lin Guangping, Zhang Yong, Li Zhuo;
Safety Officer:Wang Xinhe Xue Zhanbei
Quality Inspector:Xue Zhanbei
Material Officer:Wu Kang Zheng Chao
Labor and Wages Officer:Zhang Jing Sun Maohong
3Current Construction Progress:
1)Civil Engineering Package 1 overall project volume proportion 93%:
1、Hormone Workshop (203): Remaining miscellaneous color steel plates and openings completed. Second coat of primer on ceiling completed. Ceiling screws completed.
2PMP Workshop (204): Second coat of primer completed. Bathroom tile work completed. Ceiling screws completed.
2)Civil Engineering Package 2 overall project volume proportion 82%:
1API Workshop (202): Second-floor cleanroom color steel plates completed. Construction underway on the first and third floors. Acid-resistant ceramic tile flooring main materials determined.
2Hormone Warehouse: Plastering work 70% complete.
3Hazardous Chemicals Warehouse 1: Explosion-relief wall construction completed. NFJ metal aggregate floor casting completed.
4Maintenance Workshop: First coat of primer on walls completed. Ceiling hangers completed.
5Cleaning Center: First coat of primer for real stone paint completed.
6Comprehensive Warehouse: Masonry for axes 1-7 completed.
7Tank Area: First-floor casting of the shed completed.
8Hazardous Chemicals Warehouse 2: Foundation masonry construction completed.
9Power Center: First coat of primer on walls completed. Ceiling hangers completed.
10Boiler Room: Negative one floor wall concrete pouring completed. Reinforcement binding for the clear water pool raft slab completed.
11Comprehensive Workshop: Indoor backfilling completed.
12External Pipe Gallery: Independent foundation construction 60% complete.
3)Installation (68% complete)
1Equipment (85% complete)
2Piping (75% complete)
3Electrical (60% complete)
4Ventilation (80% complete)
5Non-standard (35% complete)
6Instrumentation (75% complete)