Yinchuan 3GW high-efficiency monocrystalline battery project construction dynamic
Release time:
2020-11-04
Source:
Yinchuan3GW High-Efficiency Monocrystalline Silicon Cell ProjectConstruction Progress
I.Project Overview
Yinchuan Economic and Technological Development Zone annual productionThe 3GW monocrystalline silicon cell and supporting project is located in the Yinchuan Economic and Technological Development Zone, Xixia District, Yinchuan City, Ningxia Hui Autonomous Region, east of Hongtu South Street, with a construction area of approximately 101078.78m²2,Building 1, the main battery factory building, covers an area of 37023.78m²2Both are single-story gantry frame steel structures. There are also special gas stations, chemical storage areas, ammonia stations, air separation stations, nitrous oxide stations, wastewater treatment plants, and other supporting facilities. It includes high and low voltage power distribution systems, electrical power systems, lighting systems, and lightning protection grounding systems.
Construction Unit: Yinchuan High-tech Industrial Development Company
Design Unit: Sichuan Hongji Architectural Design Co., Ltd.
Supervisory Unit:Ningxia Chengxin Engineering Management Consulting Co., Ltd.
Sichuan Tongchuang Construction Engineering Management Co., Ltd.
Henan Xinhengfeng Engineering Consulting Co., Ltd.
Construction Unit: Shaanxi Construction and Installation Group Co., Ltd.
Project Quality Goal: High-quality Project
II. Project Management System
Project Commander: Lan Chao
Project Manager:Wei Zhiqiang/Qi Changyun
Business Manager: Fan Peng
Technical Leader:Hao Haitao
Technical Expert: Bao Liangzhuo
Construction Workers:Hui Lulu,Huo Suicheng, Li Changhua, Zhang Chuang,Gao Feng,Li Bingfeng, Nan Yongtao,Wang Chaofan, Zhou Ke,Li Baoxian, Liu HongjiZhao Zhentuo, Dong Jiangtao, Zhu Chao, Zhao Zhihai;
Safety Officer:Kou Jianbin, Ma Huimin
Quality Inspector:Huang Shelin
Material Officer:Jiang Chenwei,Cui Jianguo, Han Weibin
Labor and Wages Officer:Le Shanshan
III. Current Construction Progress
1Civil Engineering Planned Completion Status:
1).1. No. 102 unit overall completion 95%
2. Atomization pool bottom plate reinforcement 50% complete, (atomization pool reinforcement binding 100% complete)
3. Outdoor pipe rack foundation 30% complete, (pipe rack foundation 30% complete)
4. No. 107 regulating pool steel structure installation 20% complete (regulating pool steel structure installation 90% complete)
2、MachineElectrical Installation Planned Completion Status:
1).Outdoor water supply construction completed260m (water supply and drainage network 50% complete)
2. 4.5m level row support installation 10% (10% complete)
3. No. 101 fire smoke sensor system installation 10% complete (No. 101 smoke sensor system 100% complete)
4. No. 101 fire sprinkler pipe installation 10% complete (No. 101 fire sprinkler system 90% complete)
5. No. 101 fresh air duct 15% complete (No. 101 fresh air duct 55% complete)