Construction Progress of the Ankang Old Airport Area Shanty Town Renovation - Yuehe Jiayuan Project
Release time:
2020-12-23
Source:
I. Project Overview:
1Project Introduction
Project Name: Ankang Old Airport Area Shanty Town Transformation—Yuehe Jiayuan Project
Project Address: Siling Village, Ankang High-tech Zone
Construction Unit: Ankang High-tech Zone Land Consolidation and Reserve Center
Design Unit: Beijing Hantong Architectural Planning and Design Co., Ltd.
Survey Unit: Shaanxi Changjia Construction Engineering Co., Ltd.
Supervision Unit: Shaanxi Jianxin Project Management Consulting Co., Ltd.
Construction Unit: Shaanxi Construction and Installation Group Co., Ltd.
Supervisory Unit: Ankang High-tech Zone Construction Engineering Quality and Safety Supervision Station
2Project General Overview
Ankang Old Airport Area Shanty Town Transformation—Yuehe Jiayuan Project。This project is a shanty town transformation project, mainly used for the first batch of relocation of residents whose homes are affected by the high-speed rail. The land area is145mu, with a total construction area of31square meters, and a building base area of4.6square meters. It features cast-in-place pile raft foundations, a main shear wall structure, and a commercial frame structure. There are a total of13residential buildings, two of which are26stories high, and the rest are32stories high, with a height of91meters. The basement has one floor, with a floor height of4.5mand is used for parking, civil defense, and equipment rooms. There are four commercial buildings, all of which are3stories high, as well as one building for celebrations and funerals. The design service life of the building is50years. The concrete grade ranges fromC20toC40and so on.
II. Project Management System:
Project Manager: Gao Dongliang
Deputy Project Manager: Zhang Tian
Technical Leader: Wang Jia
Construction Workers: Wang Lin, Zheng Kongfei, Han Lipeng
Safety Officers: Dong Yonghui, Liu Xia, Zhang Zhaoyuan
Quality Inspectors: Lu Wutao, Tian Jingshen
III. Current Construction Progress:
1,Currently,The exterior real stone paint, interior decoration, and water and electricity installation of Buildings 5-8 are nearing completion, and are planned to be ready for initial inspection by the end of 2020.
2,Building 3The secondary structure construction is complete, and the exterior wall insulation is underway.
3,Buildings 2, 10, and 13 were topped out in August, October, and November 2020, respectively, and are currently undergoing secondary structure construction.
4、Buildings 1, 15, and 9 are undergoing main structure construction, having reached27floors,7floors,1 floor, respectively.
80% of the exterior real stone paint for the commercial buildings of Buildings 5 and 17 has been completed, and the main structure construction of Building 16 is underway.
IV. Project Highlights:
Won first place in the Shaanxi Construction Group's third-quarter quality and safety inspection in 2019 and first place in the first-quarter quality and safety inspection in 2020.
Awarded the Outstanding Project Department of Shaanxi Construction and Installation Group Co., Ltd. in 2019 and the "Youth Shock Brigade" honorary title in 2019.
Subsequently awarded Ankang Municipal Civilized Construction Site and Shaanxi Provincial Civilized Construction Site.
Hosted the launch ceremony of the "Safety Production Month" activity in the construction field of Ankang High-tech Zone in 2020, and the "Safe Construction Site" project of Ankang High-tech Zone in 2020.
Achieved one Class II and one Class III provincial-level excellent quality management group achievements in 2020.
Hosted the 15th Ankang Municipal Construction Engineering Quality, Safety, and Civilized Construction and Dust Control On-site Observation Conference.
Ankang Municipal Civilized Construction Site and Advanced Project in Dust Control in 2020.