Construction progress of the Ankang High-tech Zone Jianmin Community Phase IV resettlement housing project (East District)
Release time:
2021-01-14
Source:
I. Project Overview:
1. Project Introduction
Project Name: Ankang High-tech Zone Jianmin Community Phase IV Resettlement Housing Project, East District
Project Address: Jianmin Middle Road, Ankang High-tech Zone, Ankang City
Construction Unit: Ankang High-tech Zone Land Consolidation and Reserve Center
Design Unit: Beijing Hantong Architectural Planning & Design Co., Ltd.
Survey Unit: Shaanxi Changjia Construction Engineering Co., Ltd.
Supervision Unit: Shaanxi Dazhan Engineering Supervision and Consulting Co., Ltd.
Construction Unit: Shaanxi Construction and Installation Group Co., Ltd.
Supervision Unit: Ankang High-tech Zone Construction Engineering Quality and Safety Supervision Station
2. General Project Overview
The total construction area of the Jianmin Community Phase IV resettlement housing project, East District, is 194,718.26㎡. It includes 9 high-rise buildings and an underground connected garage. The structural form is a frame shear wall structure. The structural safety level is Level 2, the building fire classification is Class 1, the fire resistance rating is Level 1, the basement waterproofing level is Level 1, the seismic fortification intensity is 7 degrees, and the design service life is 50 years. The residential plot ratio is 3.49, the building density is 20.55%, there are 1296 households, and a total of 4147 people. The contract duration is 580 calendar days.
II. Project Management System:
Project Manager: Gao Dongliang
Deputy Project Manager: He Jiaolong
Technical Manager: Zhang Sen
Construction Worker: Cao Zhen
Safety Officer: Dong Jing, Wang Bo, Hou Dongbing
Quality Inspector: Wang Yinbao, Lai Yumeng, Yang Bin
III. Current Construction Progress:
1. The main structures of Buildings 22 and 23 have been topped out. The secondary structure of Building 22 is completed up to the 20th floor, and Building 23 is completed up to the 15th floor;
2. The main structure of Building 25 is completed up to the 7th floor;
3. The main structure of Building 26 is completed up to the 11th floor;
4. The engineering piles for Buildings 27 and 28 have been completed;
5. The structure of Underground Garage 5 is completed from E-Y/1-14 axis;
6. Excavation of foundation pit for Buildings 29-31.
IV. Project Highlights
The project plans to achieve a civilized construction site, high-quality structure, and green construction demonstration project. Currently, the temporary construction area and site layout have been implemented according to the plan and have achieved good results. In the main construction of Buildings 25 and 26, new plastic formwork and shear wall reinforcement were used to improve the quality of the finished product. In the masonry construction of Buildings 22 and 23, the principle of masonry layout and sample-first was adhered to, ensuring the quality of masonry construction.