The Karachi Unit 2, the first overseas Hualong One reactor project participated in by Shaanxi Construction & Installation Group, has successfully achieved its first grid connection.
Release time:
2021-03-29
Source:
On March 18, local time, the first overseas Hualong One reactor project participated in by the Group Company—the Karachi Unit 2 project in Pakistan—successfully achieved its first grid connection. This is a significant milestone in the overseas construction of China's independently developed third-generation nuclear power technology, Hualong One, marking a major step towards its completion and commercial operation.
Located on the northern coast of the Arabian Sea in the Indian Ocean, the first overseas Hualong One reactor project is a significant achievement of the national "China-Pakistan Economic Corridor" and "Belt and Road" initiatives, and it is also a landmark project for China's nuclear power industry's "going global" strategy. After completion, the project will effectively alleviate the power shortage in Karachi, Pakistan's largest city.
Unit 2 will generate nearly 10 billion kilowatt-hours of electricity annually, meeting the annual electricity needs of 1 million people in the area. This is equivalent to reducing standard coal consumption by 3.12 million tons and carbon dioxide emissions by 8.16 million tons annually, which is equivalent to planting more than 70 million trees. The project's construction has also driven the development of related industries in Pakistan, providing more than 10,000 jobs for Pakistanis and playing a significant role in promoting local livelihoods and economic development.
The Group Company undertook the construction of 42 sub-projects of BOP (Balance of Plant) here. The 42 individual units are extensive and diverse, with a lot of overlapping operations, often making BOP a construction island. The project team had to make way for conventional island and nuclear island construction while also ensuring that the project was not delayed, so they planned ahead and actively coordinated resources to ensure construction progress.
On September 4, 2020, the K-2 unit's hot performance test was successfully completed. On November 28, the fuel loading was achieved. On February 28, 2021, the unit reached criticality for the first time. On March 18, the first grid connection was successfully achieved... The completion of these major milestones is due to the hard work of more than 800 employees of the Group Company.
In addition, project employees also had to overcome the "fiery weather" of nearly 50 degrees Celsius in summer and 30 degrees Celsius in winter, as well as relentless mosquito bites—a challenge to everyone's physical limits. Electric fly swatters and wind oil became standard equipment for everyone. Without vegetables, the project department became self-sufficient, cultivating vegetable plots around their living quarters, adding a touch of green to this grayish-brown Gobi desert.
Mental challenges were also a hurdle. Located far from urban areas, desolate and uninhabited, the site operates under complete closed-off management. Mobile signal is poor, internet is slow, and most people have not had a vacation back home for more than a year and a half, with the longest being two and a half years. The project department has a dedicated branch secretary and an employee activity room, regularly organizing basketball games, fitness runs, and other cultural and sports activities to enrich everyone's leisure time and alleviate the monotony of life and homesickness.
During the phased lifting of epidemic restrictions in Pakistan, the project department demonstrated the concept of win-win cooperation with Shaanxi Construction through practical actions. In addition to strengthening normalized epidemic prevention and control work, the project department also took the initiative to undertake the construction of isolation areas for owners and clients, the expansion of testing sites, and the repair of windows and doors in the Pakistani workers' camp. The project department always required its employees to prioritize the project construction goals, and after the New Year, it was the first among nine participating units to resume on-site construction.
With the grid connection and power generation of Unit 2, the Group Company's project department's construction tasks for the K2 unit are basically completed, and the focus has shifted to the completion and handover of the K2 unit and the cold test preparation for the K3 unit. The project department will make unified arrangements and deployments, allocating labor, materials, and equipment resources to strive to complete the contractual construction tasks of the K3 unit by the end of the year and proceed to the physical handover and compilation of completion documents for handover.