Construction progress of Wanhua Chemical's 280,000-ton polyalkylene polyol expansion and renovation project
Release time:
2021-02-28
Source:
I. Project Overview:
1. Project Introduction
Project Name: Installation Project for the Capacity Expansion and Renovation of a 280,000-ton Polyether Polyol Plant
Project Address: WanHua Ningbo Industrial Park, Daxie Development Zone, Ningbo, Zhejiang Province
Construction Unit: WanHua Chemical (Ningbo) Rongwei Polyurethane Co., Ltd.
Design Unit: Yantai WanHua Chemical Engineering Design Institute Co., Ltd.
Supervision Unit: Shaanxi Chengxin Construction Supervision Co., Ltd.
Construction Unit: Shaanxi Construction and Installation Group Co., Ltd.
2. General Project Overview
The installation project for the capacity expansion and renovation of a 280,000-ton polyether polyol plant, routine minor renovation projects, and maintenance projects have a contract value of 40 million yuan. The contract duration is planned to start on November 1, 2020, and to be completed on December 31, 2022.
II. Project Management System:
Project Manager: Ren Sufong
Technical Manager: Fang Wentian
Safety Officers: Dai Danbin, Wang Zhijian, Wang Hui;
Quality Inspector: Xie Liang;
Construction Foreman: Liu Xu;
Warehouse Keeper: Wang Jinqiang;
III. Current Construction Progress:
The current completed engineering output value is 4.5 million yuan. The total weight of the steel structure installation in the Class B unloading area is 20 tons. There are 50 on-site construction workers. Work completed includes: white sugar warehouse demolition (civil engineering), white sugar warehouse demolition (installation), power lines, control lines, monitoring lines and bridge demolition; bridge and terminal boxes on the west side of the factory building; the re-laying of power lines, control lines on the west side of the white sugar warehouse; protective demolition of the refrigeration room; wastewater tank and its auxiliary pipelines; demolition of the intermediate tank area; demolition of pipe racks and pipelines on the north side of the white sugar warehouse; pipelines from the equipment room to the north side of the white sugar warehouse; demolition of pipe supports and bridges on the south side of the white sugar warehouse; installation of passage pipe racks from Phase 3 to the Class C tank area; transportation of WanHua materials from the materials warehouse to the prefabrication area; demolition of the EO storage tank and its associated pipelines; manufacturing and installation of logistics park shelves; demolition of pipelines on the west side of the white sugar workshop; demolition of Class B EO wastewater tanks; addition of valves to the gas pipeline after demolition; relocation of eyewashers in Class B loading positions; repair of eyewashers in the warehouse; sealing of broken fire pipelines; cutting and sealing of fire pipelines; cutting of pipelines; demolition of the sewage pool gatehouse; demolition, installation, and auxiliary material pricing of rainwater pipes; installation of firewalls; demolition of Phase 3 purlins, etc.
IV. Project Highlights
The on-site construction plan is reasonably arranged, with comprehensive optimization of the construction organization design. The company has dispatched elite personnel to form a professional project management and construction team. Upholding the spirit of hard work and tenacious struggle, we carefully organize, manage scientifically, ensure safe production, and implement civilized construction. We strictly implement the owner's standardized management systems and procedures, completing all aspects of the project construction to high standards and high quality. During the 30-day emergency rescue operation during the Spring Festival, the tasks were completed on time and with high quality, earning praise from the owner.