Construction progress of the Yulin City YuYang ZhongNeng YuanDaTan Mining Co., Ltd. mine water deep processing project
Release time:
2021-03-31
Source:
I. Project Overview:
1. Project Introduction
Project Name: Yulin City Yuyang Zhongneng Yuandatan Mining Co., Ltd. Mine Water Deep Treatment Project
Project Address: Yuyang District, Yulin City, Shaanxi Province
Construction Unit: Yantai Jinkai Environmental Protection Technology Co., Ltd.
Design Unit:China Coal Science and Technology Engineering Group Wuhan Design and Research Institute Co., Ltd.
Supervisory Unit:Shaanxi Xiye Project Management Investment Consulting Co., Ltd.
Construction Unit: Shaanxi Construction and Installation Group Co., Ltd.
2. General Project Overview
Mine water deep treatment civil engineering, including: water treatment workshop and switch room; chemical dosing room and chemical warehouse; water source heat pump room; air compressor, sewage de-sludging and acid-base tank combined; intermediate water pool and pump room; comprehensive office building; high-density pool1; DTNF thickening pool; regulating water pool and pump room. The above-mentioned single building structure projects do not include the cement soil mixing pile foundation part of the acid-base tank and sludge dewatering room, and the comprehensive water treatment workshop. Except for the cement soil mixing pile, the earthwork excavation and backfilling are undertaken by the contractor, and the contractor must participate in and cooperate with the third-party testing process of the cement soil mixing pile.The contract amount is39683137.56Yuan,Contract duration: Planned start date: 20203Month25Day, Planned completion date: 2020Year7Month25Day.
II. Project Management System:
Project Manager:Lei Bo;
Technical Leader:Liu Yonghua;
Safety Officer:Hao Erbin;
Quality Inspector:Wang Meng;
Construction Foreman:Che Xiaogang,He Shengsheng,Duan Hongze;
MaterialsInspector:Qu Wenbo;
III. Current Construction Progress:
1. Air compressor, sludge dewatering, and acid-base tank combined building: Doors and windows installation completed, stair railings installation completed.
2. Chemical dosing room and chemical warehouse: Railings installation completed.
3. Water treatment workshop and switch room: Secondary structure completed; steel structure steel beams, purlins, roof panels, and railings completed; water treatment switch room roof waterproofing completed 30%; steel ladder installation completed.
4. High-density sedimentation tank 1: Pump room masonry completed; steel structure steel beams, purlins, roof panels, and railings completed.
5. Sludge tank and pump room: Window installation completed; railings completed.
6. Intermediate water pool and pump room: Window installation completed.
7. V-shaped filter pool: Protective railings completed.