Construction Progress of the Public Utilities and Auxiliary Facilities Project for the 600,000-ton/year High-Performance Resin and Supporting Equipment Innovation Technology Industrialization Demonstration Project of Shaanxi Jintae Chlor-Alkali Shenmu Chemical Co., Ltd.
Release time:
2021-04-26
Source:
I. Project Overview
(1)Project Overview
Shaanxi Jintaichlor Alkali Shenmu Chemical Co., Ltd.,600,000 tons/year Industrial Demonstration of Environmental Protection and Innovation Technology for High-Performance Resin and Supporting DevicesAfter completion, the project will annually utilize 1.65 million tons of coal resources in situ, increase the electricity load by 2.4 billion kWh, transform approximately 900,000 tons of rock salt in situ, and achieve sales revenue of 6.3 billion yuan. This will strongly promote the integrated development of "coal, electricity, and energy-intensive chemicals" within the Shaanxi Investment Group, while also helping to further leverage the prominent comprehensive locational advantages of Shenmu and its surrounding areas. It will drive technological progress in the industry, promote synergistic development of surrounding industries, inject new vitality into the sustained growth of the local economy.
(2)Project Introduction
1. Project Name
Shaanxi Jintaichlor Alkali Shenmu Chemical Co., Ltd.,600,000 tons/year Industrial Demonstration Project of Environmental Protection and Innovation Technology for High-Performance Resin and Supporting Devices,Public Utilities and Auxiliary FacilitiesPC General Contracting Section。
Project Address:Jinjie Industrial Park, Shenmu City, Yulin City (Zhongmiao Village)
2.Scope of Contract
Public Utilities and Auxiliary Facilities (03 Section)。PC General Contracting Section for Public Utilities, Auxiliary Facilities, Storage and Transportation, and Production ManagementThe building structures and electromechanical installation engineering are responsible for public utilities and auxiliary facilitiesConstruction engineering construction, including (but not limited to): production device construction: air compression nitrogen station, refrigeration station, circulating water station, desalination station, comprehensive pump station, inorganic wastewater treatment station, wastewater treatment station,110KV substation,shouldemergency accident water pool/rainwater monitoring pool, etc., and all device structures and electromechanical installation construction within the boundary area.
Auxiliary facilities construction (including but not limited to): central control room, central laboratory, comprehensive warehouse and spare parts warehouse, chemical warehouse, dangerous chemical warehouse, PVC intelligent three-dimensional warehouse and packaging, hazardous waste temporary storage warehouse, comprehensive repair workshop, heat exchange station, fire station and gas prevention station, weighing room, gate and guardhouse, factory-wide access control system, factory-wide general plan transportation; power supply system, heating system, gas supply system, water supply system, telecommunication system, fire protection system, corridor, bridge frame, etc. within the boundary area (excluding external corridors and affiliated external pipes and bridge frames); self-control instruments, safety facilities, fire protection facilities, occupational health facilities, environmental protection facilities, lightning protection and anti-static facilities, roads, HVAC, lighting, etc. outside each device area.
3.Participating Units:
(1) Construction Unit: Shaanxi Jintaichlor Alkali Shenmu Chemical Co., Ltd.
(2) Supervisory Unit: Zhongzi Engineering Management Consulting Co., Ltd.
(3) General Contractor: Shaanxi Construction Engineering Installation Group Co., Ltd.
(4) Design Unit: China Chengda Engineering Co., Ltd.
(5) Survey Unit: Shaanxi Tiandi Geological Co., Ltd.
4.Contract Amount and Construction Period:
(1) Contract Amount:623,944,044.43 yuan (including provisional funds (¥85,000,000);
(2) Planned Construction Period Target: Total Construction Period: 430 calendar days; Planned Start,CompletionDate: September 30, 2020-Planned Completion Date: December 3, 2021;
II.Project Management System:
Project Manager: Ma Xiaobao;
Executive Manager: Yan Yongjun;
Production Manager: Zhang Lifeng;
Chief Engineer: Xue Xinming;
Construction Supervisor: Zhang Zhongxin, Lan Jun, Shi Lei;
Safety Officer:Ma Yingjun, Wang Tongchuan, Zhao Zhong, Yang Peng;
QualityOfficer:Wu Kunxiang, Fan Heping;
Construction Worker:Li Tianyuan, Wan Quan, Wei Feng, Lei Yu, Wang Jin;
Materials Supervisor:Zhang Li;
III. Current Project Construction Progress
1.Production Device Construction:
(1) Air compression nitrogen station, refrigeration station, desalination station, comprehensive pump station,110KV substationThe concrete main body structure of the 35KV substation has been completed;
(2) shouldEmergency accident water pool/rainwater monitoring poolRaft slab construction completed;
2. Auxiliary Facilities Construction:
(1) Central control room,Central analysis roomComprehensive warehouse、Spare parts warehouse, comprehensive repair workshop,3# and 4#Main gate and guardhouseConcrete main structure is completed;
(2) Chemical warehouse, hazardous chemical warehouse, hazardous waste temporary storage、Heat exchange station,Secondary structure of the sample preparation room is completed;
(3) The main structures of the East District auxiliary substation and the West District auxiliary substation are completed;
(4) The main pipeline of the whole plant general plan has been completed;