Construction Progress of Gaoxin Tian Valley Elegant Residence Project, South Block, Second Section
Release time:
2021-05-31
Source:
I. Project Overview
1. Project Introduction
Project Name: GaoxinTiangu Valley Residence Project South Block Section 2
Project Address: North of Tiangu Fourth Road, East of Yunshui Third Road, West of Yunshui Second Road, Gaoxin District, Xi'an
Construction Unit: Xi'an Gaoxin Technology Industrial Development Zone Real Estate Development Co., Ltd.
Design Unit: Zhonglian Northwest Engineering Design and Research Institute Co., Ltd.
Exploration Unit: Machinery Industry Exploration and Design Research Institute Co., Ltd.
Supervision Unit: Xi'an Maohua Engineering Construction Supervision Co., Ltd.
Construction Unit: Shaanxi Construction and Installation Group Co., Ltd.
SupervisionUnit: Xi'an Gaoxin District Construction Engineering Quality and Safety Supervision Station
2. General Project Overview
Total building area of this project137149.23m2,Contract price:1165617397.82 yuan,Shear wall structure,Including high-rise residential buildingsBuilding 12 (21/-2 floors), Building 16 (24/-2 floors), Building 17 (25/-2 floors), Building 20 (25/-2 floors); Commercial/supporting Building 13 (6/-2 floors); Underground parking garage (-2 floors); Gatehouse 1 (1 floor); Gatehouse 2 (1 floor)。Contract duration---Start date:August 15, 2020,
Completion date:August 25, 2023.
II. Project Management System
Project Manager: Zhang Xu
Executive Manager: Fan Wenjin
Deputy Project Manager: Wang Luey
Technical Leader: Gao Lei, Su Peilong
Construction Workers: Lu Mou, Kang Jiaxi, Li Zonglin, Zhang Dong, He Jianjun, Pang Xinji,
Li Yuhang, Liu Ruichao, Fang Qiang, Gao Congyu, Zhao Sen, Guo Zhou, Xue Tianyang,
Li Shaoteng, Liu Dong, He Zhen, Xiao Yikun, He Chunlei
Safety Officers: Zhang Tieshan, Xue Zhanbei, Yu Zhaoyang, Su Jianzhi
Quality Inspectors: Yuan Fei, Chen Wei
III. Current Construction Progress
1.Building 12The main structure construction is up to2floor,2floorPCcomponents and aluminum formwork installation are completed; the climbing frame is undergoing pre-entry construction technical briefing, and is about to organize the entry of climbing frame materials and entry acceptance.
2.Building 13Main structure construction up to ±0.00,Due to changes, there are no drawings above ±0.00。
3.Building 16The main structure construction is up to2floor,2Aluminum formwork installation completed,PCComponents are being installed.
4.Building 17Main structure construction up to-1floor.
5.Building 20Main structure construction up to1floor.
6. Underground parking garage construction completed30%。
7. Electromechanical installation: Cooperate with civil construction for reservation and pre-embedding, synchronizing with civil construction progress.
IV. Project Highlights
Passive near-zero energy consumption building, prefabricated interior partition walls, aluminum formwork optimized for one-time successful installation, electromechanical installationBIM optimization, construction site material acceptance, process acceptance100%Full coverage of signboards.Project excellence goals Shaanxi Province“Chang'an Cup”, Shaanxi Province “Green Construction Demonstration Project”, Shaanxi Province High-Quality Structural Engineering. The quality management process should strictly follow “plan first, sample leading, process control, continuous improvement”.