Shaanxi Construction and Installation Group undertakes the construction of Southeast Asia's largest integrated phosphate chemical project - the first yellow phosphorus electric furnace of the Malaysia Integrated Phosphate Chemical EPCC project is put into operation
Release time:
2021-07-14
Source:
On July 1st, the first 12,000-ton yellow phosphorus furnace of the Southeast Asia's largest integrated phosphatic chemical project—the Malaysia Integrated Phosphatic Chemical EPCC project, undertaken by the group company—successfully switched on and heated up. After six days of trial operation, on July 7th, with the command of the on-site general commander, the No. 4 yellow phosphorus furnace was successfully ignited at one time, marking a significant step towards the full-scale production and delivery of the project, and contributing the Shaan'an strength to the "Belt and Road" initiative.
This project is an integrated project of planning, design, procurement, and construction undertaken by the group company, representing the largest EPCC project (turnkey project), the largest single industrial installation project, and the largest international market project in its history. It is also a milestone project of the group company's "Belt and Road" initiative. Comprising a 48,000-ton-per-year yellow phosphorus unit, a 75,000-ton-per-year thermal phosphoric acid unit, a 60,000-ton-per-year food-grade phosphoric acid unit and other facilities, it is the largest phosphate plant in Southeast Asia.
By September 2020, the project construction was basically completed. There were 268 sets of moving equipment in the whole plant. The core tasks became the single-machine, joint commissioning, start-up, and compilation and handover of construction technical documents for the yellow phosphorus unit, thermal system and plant-wide facilities including 46 work areas. At this time, the COVID-19 epidemic in Malaysia was still very serious, and the entry of domestic and foreign design, construction, start-up, and commissioning professionals and materials was severely affected. Furthermore, the local government, owner's management department, experts, and consultants had different opinions, making the project's progress extremely difficult.
To ensure the smooth progress of the commissioning work, the project department made unified arrangements and deployments, allocating elite personnel and assigning dedicated personnel to each key link. Du Jianxue, a technical expert who hadn't gone home for two years, worked day and night, interpreting the meaning of "striving until one can't strive anymore, and fighting until one is moved by oneself"; Wang Xijun, the installation manager, was responsible for the rotary equipment, personally solving the problems of large vibration and heat generation of the submersible pump during the single-machine test; Zhang Liguo, the chief engineer, was responsible for the complete sets of equipment. Due to the impact of the epidemic, the factory's technicians could not arrive at the site for on-site operation, forcing him to study the drawings submitted by the manufacturer day and night, remotely communicating the performance, principles, structure, and applications of each equipment, finally successfully completing the commissioning and trial operation of the complete sets of equipment; Zhang Weitao, the design manager, was responsible for the fire-fighting facilities, coordinating with the design institute and the owner to complete the commissioning and operation of the fire-fighting and automatic fire extinguishing systems before the phosphorus furnace transformer was energized.
Based on the single-machine test, the project department summarized the procedures and key points of the subsystem joint commissioning. During the joint commissioning, the professional foreman gave instructions, the start-up personnel operated, the foreman monitored, the owner's process engineer gave instructions, and the owner's operators operated. The personnel of each position cooperated with each other, greatly improving the commissioning efficiency of subsystems such as the phosphorus water circulation system, tail gas conveying system, and slag quenching water circulation system.
For more than 80 days and nights, all employees of the project department worked against the clock every day in the "hot weather" of more than 30 degrees Celsius, successfully completing the single-machine and joint commissioning of moving equipment, yellow phosphorus units, thermal systems, and plant-wide facilities work areas. Finally, the trial operation of the first yellow phosphorus furnace was ushered in.
The "start-up and operation" of the first yellow phosphorus furnace lays a solid foundation for the subsequent operation of the phosphoric acid system and other devices. The project department is confident that it will overcome all difficulties, race against time, complete the construction target as scheduled, and offer a gift to the 100th anniversary of the founding of the Communist Party of China!
Comprehensive, project, system, yellow phosphorus, debugging, device, commissioning, maximum, operation, start-up