Construction progress of the Xi'an International Football Center project
Release time:
2021-07-24
Source:
I. Project Overview
1.1 Project Introduction
Construction Location: Fuxing Avenue, Xi'an City, Shaanxi Province
Construction Content: Steel structure ring shell, audience stands, ordinary audience rooms, VIP audience rooms, athlete rooms, management offices, news media rooms, AFC office rooms, competition and management technology rooms, commercial rooms, 1875 underground and above-ground parking spaces, and a football field, etc.
Total Construction Area: The project covers an area of 180,000㎡, with a total construction area of approximately 280,000㎡. The plan size is 450m wide in the east-west direction and 560m long in the north-south direction, with a seating capacity of 60,000.
1.2 Main Project Responsibilities
Construction Unit: Xi'an International Football Center Project Construction Management Office
Construction Agent: Shaanxi Xixian Central Business District Construction and Development Co., Ltd.
Survey Unit: Northwest Comprehensive Surveying and Design Institute
Design Unit: Shanghai Architectural Design & Research Institute Co., Ltd.
Supervision Unit: Guangzhou Zhujiang Engineering Construction Supervision Co., Ltd.
Construction Unit: Shaanxi Construction Engineering Group Co., Ltd.
1.3 Overview of Electromechanical Installation Design
This project's electromechanical installation includes water supply and drainage and fire protection engineering, heating and ventilation and air conditioning engineering, and strong current engineering.
Water supply and drainage engineering includes domestic water supply, domestic hot water, recycled water, sewage, rainwater, fire hydrant water supply, and automatic sprinkler fire extinguishing system.
The HVAC system mainly includes air conditioning and heating and cooling source systems, air conditioning systems, ventilation systems, mechanical smoke exhaust systems, and heating systems. This project uses a central air conditioning system. There are many large-scale equipment in ventilation and air conditioning, and the installation locations are relatively dispersed.
The strong current system mainly includes: power distribution system, low-voltage distribution system, lighting system, and lightning protection grounding system. This project has high power supply requirements for the building's power distribution system, high precision for the intelligent lighting control system, and requires a stable and reliable power supply to ensure the normal progress of the competition and broadcasting. To meet the requirements of different training, competitions, high-definition television broadcasting, and energy conservation and environmental protection, various control modes need to be adopted to meet the actual on-site applications and illuminance requirements.
II. Project Management System
Project Manager: Zuo Leian
Project Technical Leader: Li Xiaxi
Construction Workers: Qian Cong, Li Jizhong, Qin Nan, Tian Xipeng, Gui Jinrui, Cui Xuening, Han Keyang
Quality Inspector: Hu Jianmin
Safety Officer: Wang Kai
Materials Officer: Han Ce
Documentarian: Liu Lining
III.Current Construction Progress
1. Electrical: 100% of the reserved and embedded work for the electrical south area is completed in coordination with the main structure, 100% of the lightning protection grounding is completed in coordination with the main structure, and the bridge frame support is starting to be installed. 100% of the reserved and embedded work for the east area is completed in coordination with the main structure, 100% of the lightning protection grounding is completed in coordination with the main structure, and 30% of the bridge frame support on the second and third floors is completed.
2. Piping: The rainwater pipes on the first floor of the south area, S67-S72 axis stands, are installed. The buried rainwater and sewage pipes and siphon rainwater pipes from S70-S76 are installed, and 50% of the first-floor sprinkler pipes are installed. 100% of the sleeve embedding is completed in the east area, and 80% of the buried pipes are installed.
3. HVAC: 20% of the air ducts have arrived on the first floor of the east area, and the air ducts on the first floor and mezzanine of the south area are being prefabricated. 20% of the air duct installation on the first floor of the south area is completed.