22 Project - Xi'an Project Construction Update
Release time:
2021-09-21
Source:
I. Project Overview
1. Project Introduction
Project Name: Project 22—Xi'an Project
Project Address: Pangguang Street, Huyi District, Xi'an City
Construction Unit: Project 22—Xi'an Project Preparatory Office
Design Unit: China Construction Northwest Design and Research Institute Co., Ltd.
Survey Unit: Northwest Comprehensive Survey and Design Research Institute Co., Ltd.
Supervision Unit: Xi'an Aerospace Construction Supervision Co., Ltd.
Construction Unit: Shaanxi Construction Engineering Group Co., Ltd.
Supervisory Unit: Xi'an High-tech Zone Construction Project Quality and Safety Supervision Station
2. General Project Overview
|
Serial Number |
Project |
Content |
|||
|
1 |
Architectural Function |
Group Public Building |
|||
|
2 |
Architectural Features |
The exterior is designed in an antique style, with a titanium zinc roof and exterior walls made of glass and stone curtain walls. |
|||
|
3 |
Building Area |
Total Building Area |
83150.95㎡ |
||
|
Underground Building Area |
35148.14㎡ |
Above-Ground Building Area |
48002.81㎡ |
||
|
4 |
Number of Building Stories |
Underground |
2 floors |
Above-ground |
4 floors |
|
5 |
Building Story Height |
Main Building |
Standard Floor |
5.1m |
|
|
Top Floor |
6.3m |
||||
|
6 |
Building Height |
Total Building Height |
44.5m |
Indoor and Outdoor Elevation Difference |
0.45m/1.318m |
|
7 |
±0 Elevation |
The main building is 518.40/540.9, and other building numbers are different. |
|||
Construction Start Date:February 1, 2021,
Completion Date:December 31, 2021.
II. Project Management System
Project Manager: Cao Qiankun
Deputy Project Manager: Bai Haonan
Technical Manager: You Qing
Construction Workers: You Qing, Zhang Xiaohua, Liu Yan, Wu Xi'an
Safety Officer: Cao Feng
Quality Inspector: Li Qichao
III. Current Construction Progress
Building 9#: Fire system completed to 90%, emergency lighting system completed to 90%;
Building 12#: Fire system completed to 95%, emergency lighting system completed to 95%, ventilation system completed to 95%;
Building 17#: Fire system completed to 90%, emergency lighting system completed to 90%, smoke exhaust system completed to 90%;
Building 18#: Fire system completed to 90%, emergency lighting system completed to 90%, smoke exhaust system completed to 90%;
Second Construction Area (Buildings 1, 2, 3)
Building 2#: Fire system completed to 20%, emergency lighting system completed to 30%;
Building 3#: Fire system completed to 20%;
Third Construction Area (Buildings 4, 5, 6, 7)
Building 4#: Emergency lighting system completed to 90%, smoke exhaust system completed to 90%;
Building 5#: Fire system completed to 70%, emergency lighting system completed to 70%, smoke exhaust system completed to 90%;
Building 6#: Fire system completed to 90%, air conditioning water system completed to 90%, emergency lighting system completed to 90%, ventilation system completed to 90%;
Building 7#: Fire system completed to 90%, air conditioning water system completed to 90%, emergency lighting system completed to 90%, ventilation system completed to 90%;
Dynamic, Complete, 90, System, Emergency Lighting, Fire System, Engineering, Construction, Project, Xi'an