On June 30, the Yanchang 694 natural gas surface gathering EPC project of Shaanxi Construction Installation Group in Fuxian County was successfully completed two months ahead of schedule. The owner awarded the project party branch the honorary banner of "Demonstration Jointly Built Branch, Team Tackling Difficulties!" The achievement of this handover target has laid a solid foundation for the project's production and operation, serving as an effective "certification" of Shaanxi's brand strength and continuing the successful cooperation with the owner, Yanchang Petroleum Group.
The project is located in Zhiluo Town, Fuxian County, Yan'an City, and is a key project in Shaanxi Province.It is a powerful measure and concrete action for Yan'an City to implement the "dual carbon" action and promote green development. After completion and commissioning, it will effectively alleviate the shortage of natural gas supply during peak seasons in the province, ensuring the demand for natural gas from downstream enterprises and residents, contributing to the upgrading of Yanchang Petroleum's 15 billion cubic meter large gas field, and injecting fresh vitality into local economic development.
SinceSince the start of construction in September 2021, more than 70 management personnel and more than 3,800 front-line construction personnel of the project department have overcome various difficulties such as the epidemic, strong autumn rains, and cold winters, actively coordinated with suppliers and local government departments to ensure that materials and equipment arrived at the site in a timely manner. Leaders took the lead in command, and functional departments provided services at the front line. While ensuring quality and safety, the project team aimed at "guaranteeing daily work progress" to fully promote the project construction and ensure that the node targets were achieved on schedule. Project manager Geng Xiaojun said: "Although the construction period is tight and the tasks are heavy, the enthusiasm of all project personnel has only increased, because everyone has a common goal in mind."
Next, the project team will take the handover as a new starting point, give full play to the role of the party branch's fighting fortress and the exemplary role of Party members, ensuring that personnel are not withdrawn, services are not reduced, and enthusiasm is not slackened. The team will increase technical support and conduct comprehensive coordination with the owner's quality, safety, and production departments, cooperating well with the joint commissioning, system airtightness, and material production.