Shaanxi Construction & Installation Group's Xianyang LNG Storage Facility liquefied natural gas unit EPC project successfully put into operation
Release time:
2022-12-02
Source:
First Engineering Company
Recently,Shaanxi Construction and InstallationGroup, as a member of the consortium,The Xianyang LNG storage facility supporting liquefied natural gas plant project, which it EPC contracted, has been successfully put into operation. This effectively improves Xianyang's natural gas reserves and emergency response capabilities, makes up for the shortfall during peak winter gas consumption, and is of great significance to promoting energy structure adjustment and air pollution control.
The project is located in Podi Village, Junma Town, Liquan County, Xianyang City, Shaanxi Province. A new200,000 m³/d liquefied natural gas planthas been built, which is an important livelihood project for Xianyang City.
Since the start of the project, all management and construction personnel of the project department have fought against the scorching heat and severe cold, overcome the adverse effects of the epidemic, and made scientific plans and arrangements for construction. At the same time, they have utilized advancedBIM technology, prefabricated and assembled modules in advance, and used advanced laser detection instruments to ensure high quality and standards in project construction, winning praise from the owner and all parties.
To ensure the project's success on the first start-up, from compressor debugging to linkage testing and material feeding testing, all employees of the project department worked together, sticking to the front line,working in 24-hour shifts. After 12 consecutive days of unremitting efforts, the plant was successfully started up for the first time, laying a solid foundation for subsequent completion and acceptance.

Related News
2022-05-05