Successfully 'closed the loop' after crossing the Qinling core area!
Release time:
2023-12-06
Source:
The Fourth Engineering Company

Recently, the Liuba to Fengxian natural gas pipeline project (Phase 1), constructed by Shaanxi Construction and Installation Group, successfully completed the final pipe welding at the intersection of Liuba County and Fengxian County in the Qinling Mountains core area, successfully meeting in the middle.The "completion" marks the end of the construction of the longest controlling project in this project.
The project passes through the Qinling protected area, located from Shimenzi Village, Yuhuangmiao Town, Liuba County to Sanguandian Village, Liufengguan Town, Fengxian County, with a length of3.35 kilometers through the Qinling protected area, of which 1.52 kilometers pass through the Qinling core protected area. This area has a large elevation difference, with the highest elevation at 1652.38 meters, the lowest elevation at 1031.72 meters, and a difference of 620.66 meters, and the slope of the mountain body is large, with the slope angle reaching up to 72 degrees in some areas.
Based on the actual situation, the project department prepared a special construction plan, organized experts to conduct on-site investigations, and successfully passed the expert review. During the construction, the project department paid great attention to ecological environmental protection, strengthened fire control, shortened the construction period, and strictly implemented the measures in the construction plan. The construction operation area in the core area is strictly controlled within a reasonable range. Faced with the wide river channel, large water flow, and high-quality requirements of the Baohe crossing Bao Han Line relocation section, the project department successfully completed the Baohe crossing using the cofferdam secondary diversion construction method; faced with the extremely difficult construction in the Qinling protected area and the inability to use mechanical transportation and ditch digging, the project department manually excavated the pipe ditch and used a winch and cableway to complete the pipe transportation work. Two teams worked from the bottom of the Qinling Mountains in Liuba and Fengxian County towards the top of the mountain, and after50 days of unremitting efforts, hundreds of construction personnel overcame various difficulties such as landslides, cold weather, falling rocks, and wild animal attacks, and successfully met at the top of the mountain to complete the "completion" under the premise of ensuring safety, fully demonstrating the excellent style of Shaanxi people who are "especially able to fight and especially able to endure hardship", laying a solid foundation for the project to achieve line connection as soon as possible.
The Liuba to Fengxian natural gas pipeline project starts from Hexi Village, Jiangkou Town, Liuba County, Hanzhong City, at the existing Bao Han Line gas pipeline (mainline opening), and ends at the newly built Fengxian terminal station in Shilidian Village, Shuangshipu Town, Fengxian County, Baoji City. The route runs from east to west through Jiangkou Town and Yuhuangmiao Town, Liuba County, Liufengguan Town and Shuangshipu Town, Fengxian County, with a total length of approximately71.59 kilometers. Among them, there are 4 medium-sized river crossings, 126 small river crossings, 1 Bao Han Expressway crossing, 3 G316 National Highway crossings, 4 G244 National Highway crossings, and 3 X301 County Road crossings. Shaanxi Construction and Installation Group is responsible for the construction of a total line length of 37.92 kilometers, including 3.4 kilometers in the Qinling protected area and the Qinling core protected area. After completion, it will provide higher-quality clean energy for the green development of enterprises along the line and the happy life of the people, and has good economic and social benefits.