The Yinchuan Sapphire Project has successfully passed its completion acceptance inspection.
Release time:
2023-12-20
Source:
Seventh Engineering Company

Recently, the Shaanxi Construction Installation Group Yinchuan Economic Development Zone Industrial Sapphire Crystal Manufacturing and Processing Project (Phase I) expansion and electromechanical equipmentEPCThe general contracting project has successfully passed the completion acceptance. The acceptance team conducted an on-site inspection of the project construction and unanimously agreed that the project construction meets the design document requirements, the construction procedures are standardized, the completion documents are complete, and the engineering quality and comprehensive evaluation level are both qualified, agreeing to the project completion acceptance. As the largest sapphire production base in China, after the completion of this project, it will mainly be invested in the production of high-end semiconductor materials and applications in the consumer electronics field, and will play a positive role in promoting the development of the electronic information industry in the Ningxia Hui Autonomous Region.
The project covers an area of51132.38square meters, with a construction area of67800square meters, installing576crystal growing furnaces, mainly producing300kilogram-level sapphires. Industrial sapphire is an important basic material for modern industry, with characteristics such as high strength, high hardness, good light transmittance, and excellent dielectric properties. It is an important material supporting the development of energy conservation and environmental protection, new generation information technology, new energy vehicles, and other industries, and is widely used in optoelectronics, communications, and medical fields. Since the start of construction, the project department has insisted on giving equal importance to quality and speed, and has carried out high-quality, high-efficiency, and high-standard construction, winning high recognition from the owner. Faced with the technical problem of abnormal fluctuations in the power grid, the project department adopted new technologies to overcome the difficulties, ensuring that the output voltage seamlessly connects to the rated value and protecting the normal operation of the load. Faced with the huge amount of steel structure engineering of the pipe gallery system, it utilizesBIMto deepen the integration of structural, architectural, and electromechanical models, conduct pipeline collision checks, and control the purification ceiling height, achieving collaborative design and visual handover of various electromechanical specialties to ensure that it is excellent on the first try.
According to the pipeline layout, the project developed a comprehensive support system to increase net space. Accessories and valve groups use factory-prefabricated technology, improving construction quality while effectively improving construction progress, achieving reasonable equipment layout, neat bases, aligned valves, and orderly instruments. The purification professional construction carried out secondary typesetting based on the original design drawings, and during installation, it ensured that the vertical and horizontal levels are aligned, and the seams between plates are tight, ensuring overall tightness and aesthetics.
Related News
2023-10-27