A fresh start, a new beginning,2024At the beginning of the year,Shaanxi Construction and Installation Group's various projects quickly adopted a spirit of seizing the day and striving for excellence,Launching a wave of rapid development,Working hard for the first quarter,Using practical actions and achievements to make a good start and lay a solid foundation for the annual goals and tasks。
Ningxia Longi Green Energy102The workshop's peripheral infrastructure and electromechanical system restoration project successfully passed the completion acceptance inspection, delivering a satisfactory result for the client. The project is located in the Yinchuan Economic and Technological Development Zone, Ningxia Hui Autonomous Region, covering an area of approximately1.9tens of thousands of square meters, mainly producingPERCsolar cells. The project team adhered to the corporate spirit of "dedication, trustworthiness, taking responsibility, building high-quality products, and pursuing excellence," continuously optimizing the construction plan, overcoming difficulties such as the coexistence of multiple professions at the construction site, complex environment, and high construction difficulty, and completed the construction task on schedule and with high quality, adding luster to the company's Brand.

Huaneng Luoyang Thermal Power20MWDistributed photovoltaicEPCproject's first batch of photovoltaic power generation successfully connected to the grid. The project is located in Luoxin Industrial Cluster Zone, Xin'an County, Luoyang City, Henan Province. The total roof area of the building is approximately1.08tens of thousands of square meters, installing high-efficiency monocrystalline silicon550Wpphotovoltaic modules2326units, with an estimated annual power generation of176.5tens of thousands of kWh. It adopts a "self-generation and self-use, surplus power to the grid" model for grid-connected power generation, with characteristics such as land saving, fast investment, and mature technology, effectively promoting the company's green transformation and development.
The main body of the Zheng'an to Wuchuan natural gas pipeline project has been completed and is ready for commissioning. Located in Wuchuan County, Zunyi City, Guizhou Province, this project is a key livelihood project of the Guizhou Province natural gas "county-county connectivity" plan, with a total length of50.8kilometers, a diameter of400millimeters, a design pressure of6.3megapascals, and an annual gas transmission volume of4.4100 million cubic meters. After commissioning, it will effectively optimize the local energy structure, reduce emissions from various urban users, improve ambient air quality, improve residents' living standards, reduce enterprise costs, and promote high-quality economic development in the region.
Xi'an High-tech·Tiangu Ya She project passed the pre-acceptance inspection for completion. Located north of Tiangu Fourth Road, east of Yunshui Third Road, and west of Yunshui Second Road in Xi'an High-tech Zone, the project has a total construction area of13.7tens of thousands of square meters. It is the first passive ultra-low energy consumption Community in Northwest China, with a comprehensive energy saving rate of90%and can achieve comfortable living quality with constant temperature, humidity, oxygen, quietness, and cleanliness.