Huainan Jingyang 200MW Photovoltaic + Ecological Governance Power Generation Project Achieves Full Capacity Grid Connection in the Year of Quality Improvement
Release time:
2024-07-04
Source:
Party Committee Political Department

Recently, the Huazhong Jingyang 200MW photovoltaic + ecological governance power generation project, undertaken by Shanjian Installation Group,achieved full-capacity grid connection.。After the project is connected to the grid and starts generating electricity,,the estimated average annual power generation during the operational period is280 million kilowatt-hours.,This saves approximately90,000 tons of standard coal per year.,It will effectively improve the utilization rate of clean energysources.,This is of great significance to further improve the local ecological environment,and promote economic development.。
As a typical domestic mountain photovoltaic project, this project includesfour independent projects: a 110KV substation, a 110KV transmission line, a 35KV power collection line, and a photovoltaic field. The photovoltaic field covers more than 8,000 mu (approximately 533 hectares), spans 13 kilometers from east to west, and 3.5 kilometers from north to south. The on-site geological conditions are complex, with more than 30 mountains of various sizes. The mountains are saddle-shaped, interspersed with ravines and historical abandoned mine pits, with an average slope of over 40 degrees.
Focusing on the "June 30" grid connection goal, the project team implemented a reverse schedule, using a visual management board and assigning responsibilities. A work mechanism of daily reports, weekly summaries, and monthly scheduling was established, ensuring that every task is monitored, implemented, and managed, to ensure the smooth progress of each process. In response to challenges such as difficult material transportation, complex foundation design, and high environmental protection requirements on site, the project department, based on the site's terrain conditions, adopted a "tailored approach," using flexible and fixed support structures to reduce land use costs. Materials were transported using a comprehensive three-dimensional transportation system involving drones, winches, and mountain transportation single and double-track slides. By fully utilizing the advantages of EPC project management, strengthening safety management and strictly controlling quality, the 200MW grid connection task was completed as scheduled, delivering a satisfactory result to the client.
Related News